Kitchen-installation RAMS should connect the approved design to the actual units, worktops, appliances, services, substrates, workforce, tools, products and room. They should explain how the area will be released, materials delivered and handled, cabinets and worktops installed, dust controlled, interfaces checked and completed work protected.
“Deliver and fit the kitchen” is not a complete method. The document should identify current drawings and schedules, scope boundaries, delivery and storage arrangements, fixing information, service controls, cutting methods, worktop arrangements, access equipment, product assessments, inspection points and stop-work conditions.
Coordinate the method with the manual-handling RAMS guide, the drilling and fixings guide, the construction COSHH guide and the project's Construction Phase Plan.
Define the kitchen-installation task and its boundaries
State which rooms and plots are included and whether the work covers unloading, distribution, base and wall cabinets, tall units, panels, doors, plinths, handles, trims, worktops, sinks, appliance positioning, sealants, protection and waste. Identify who provides templates, cut-outs, specialist lifting, connections, testing and commissioning.
Separate fitting from specialist work. Gas connections, fixed electrical alterations or energisation, plumbing commissioning, ventilation design, structural alteration and stone fabrication require the appropriate appointment, information and competence. A kitchen fitter should not inherit those responsibilities merely because the activities occur in the same room.
Use the current kitchen design and manufacturer information. Do not assume cabinet positions, clearances, ventilation, wall construction, fixing capacity, worktop support, service routes or appliance connection requirements.
What information should be obtained before installation starts?
Confirm, where relevant:
- the latest room layouts, elevations, setting-out dimensions, unit schedule, worktop details and appliance schedule;
- the wall, floor and substrate construction, condition, load capacity and approved fixing details;
- surveyed service positions, isolations, safe drilling zones and the person authorised to confirm readiness;
- unit, appliance and worktop dimensions and weights, centres of gravity, fragile edges and manufacturer handling information;
- delivery booking, unloading, storage and distribution routes, including stairs, door openings, floor protection and occupied areas;
- which components arrive pre-cut or pre-drilled and which adjustments are genuinely necessary on site;
- the worktop material, fabrication status, template approval, cut-outs, joint details, support, lifting aids and installer competence;
- the specified fixings, brackets, rails, adhesives, sealants, cleaners and other products, with current instructions and safety data;
- the tools, extraction, vacuum, access equipment and electrical supply arrangements, including checks and operator competence;
- other trades, residents or building users, release of completed services and finishes, escape routes and noise or dust restrictions; and
- hold points for room release, setting out, service and fixing verification, first-off installation, worktops and final acceptance.
Write the method in the order the work will happen
A project-specific sequence may cover:
- confirming the current drawings, schedules, manufacturer information, room and scope boundaries;
- checking room release, substrate condition, services, isolations, access, lighting, ventilation and interfaces;
- booking deliveries, checking loads and distributing components without blocking routes or damaging finished work;
- setting out datum lines, cabinet positions, worktop height, appliance openings and service interfaces;
- checking wall construction, concealed-service information and approved fixing locations before drilling;
- assembling and installing base, tall and wall units in the planned order with temporary stability where needed;
- checking level, plumb, alignment, fixings, supports and openings before worktops or appliances conceal access;
- receiving, lifting and installing worktops using the approved support, joint and cut-out information;
- positioning appliances and sinks without making connections outside the fitter's assessed scope;
- installing doors, panels, plinths, trims, handles and specified sealants;
- completing inspections, recording defects, protecting the installation and coordinating specialist testing; and
- removing waste and reopening the area only when authorised.
Critical controls to address in kitchen-installation RAMS
Deliveries, storage and manual handling
Obtain weights and dimensions for cabinets, appliances and worktops. Plan routes and delivery sequence so items can be moved near their point of use without repeated handling. Use suitable trolleys, panel carriers, lifting frames, suction devices or mechanical assistance where the assessment requires them.
Worktops and tall appliances can be long, fragile, top-heavy or difficult to grip. Check doorways, stairs, turns, floor condition and landing areas before movement. Team handling and technique training can support a planned lift, but they do not replace avoiding or mechanising a high-risk lift.
Substrates, fixings and concealed services
Confirm that walls and floors are suitable for the specified installation. Use fixing details appropriate to the actual substrate, cabinet load and manufacturer requirements. Stop for unknown build-ups, loose or damaged material, unexpected voids, unconfirmed fixing capacity or a design conflict.
Use current service information and the project's safe system for locating concealed services. Isolate where required, use suitable detection and verify the proposed drilling position before starting. Scanning does not prove an area is clear, so the method should combine information, inspection, detection, controlled drilling and stop-work rules.
Wood-based products, cutting and sanding
Reduce site cutting through accurate measurement, pre-cut components and dedicated work areas. Where powered cutting or sanding is necessary, use suitable on-tool extraction connected to an M- or H-class unit and maintain secure connections and adequate airflow. Select RPE from the assessment; tight-fitting RPE requires face-fit testing and compatibility with other PPE.
Use an M-class industrial vacuum or another assessed dust-control method for cleanup. Do not dry sweep or use compressed air. Consider health surveillance where workers may inhale wood dust, which can cause asthma and, for hardwood dust, cancer.
Stone and engineered-stone worktops
Plan natural or artificial stone worktops so cutting, shaping, polishing, sink holes, tap holes and optional drainage grooves are completed in a suitably equipped workplace before delivery. Accurate measurement and approved fabrication details reduce the need to create respirable crystalline silica dust on site.
If a minor modification can only be made on site, use a well-ventilated segregated area with restricted access, ideally outdoors, and the assessed water-suppression or on-tool extraction arrangement connected to an M-class vacuum. Provide appropriate RPE, wet or M-class-vacuum cleanup and controlled slurry or dust disposal. Uncontrolled dry cutting, dry sweeping and compressed-air cleaning are not acceptable defaults.
The RAMS should also address worktop weight, fragile edges, lifting devices, temporary support, joints and installer competence. A routine fitting method does not authorise uncontrolled fabrication or modification beyond the assessed scope.
Work equipment, electricity and low-level access
Select saws, routers, drills and other equipment for the material and operation. Check guards, cutters, bits, workpiece support, cables, extraction and emergency controls before use. Restrain components and keep hands clear of the cutting path. Define the site's electrical supply, protection and lead-management arrangements rather than relying on a test label alone.
Use a suitable platform for wall units, cornices, extract components or high fixings that cannot safely be reached from the floor. Select access equipment for the height, duration, reach, tools, materials and floor condition; do not work from units, worktops or makeshift platforms. The stepladders and podium steps guide explains the assessment points.
Adhesives, sealants, cleaners and occupied areas
Prepare task-specific COSHH assessments from current labels, safety data and manufacturer instructions. Control skin and eye contact, vapours, spills and curing-area access, and confirm adequate ventilation. Check glove material and use conditions rather than listing “gloves” without a basis.
Separate residents, building users and other trades from unloading, cutting, drilling and installation. Protect escape routes, completed floors, doors and finishes. Coordinate noise, dust, ventilation and service isolations, and keep incomplete units, projecting fixings, tools and packaging from creating instability, cuts, trips or blocked routes.
What should inspection and records cover?
Identify who accepts room readiness, wall and floor condition, service positions, fixing details, setting out, first-off work, worktop fabrication and specialist connections. Record hold points before cabinets, panels, worktops or appliances conceal services and fixings.
Final checks should address level, plumb, alignment, secure cabinets, supports, worktop joints and edges, appliance openings and ventilation clearances, door and drawer operation, sealant interfaces, damage, cleanliness and protection. Use the current design and manufacturer information for acceptance criteria. Record defects, corrective work and the person authorising handover.
When should the RAMS be reviewed?
Review the method when the drawing, room, substrate, fixing, unit, worktop, appliance, service, product, access, delivery route, tool, workforce, occupied-area interface or programme changes. Stop and reassess after discovering unexpected services, asbestos concerns, an unsuitable wall, damaged equipment, an unplanned stone cut, uncontrolled dust, a defective component or a near miss.
Brief the team on the approved design, scope boundaries, sequence, exposure controls, hold points and stop-work conditions. Principal Contractor acceptance does not make a generic document suitable or transfer the contractor's duty to plan, manage and monitor its work.
When routine kitchen-installation RAMS are not enough
This scope does not approve gas work, fixed electrical alterations or energisation, plumbing commissioning, ventilation design, structural alteration, asbestos disturbance, unplanned stone fabrication, lifting operations outside the assessed method, or access requiring a separately designed system.
It also does not replace approved kitchen drawings, service information, fixing design, manufacturer instructions, COSHH assessments, exposure assessment, specialist connection and test records or client handover requirements. Obtain the relevant competent design, trade or project input before those activities proceed.
Can a kitchen-installation RAMS template be used?
A relevant template can provide a useful structure, but it cannot know the room, design, wall construction, service positions, units, worktops, appliances, products, equipment, access or interfaces for the project.
The Kitchen Installation RAMS template is available in the IMERI H&S Partners RAMS shop. Check that its named scope matches the work. A competent person must assess and adapt it to the project, drawings, services, substrates, components, products, equipment, workforce and Principal Contractor requirements, then brief the workforce.
Buying or completing a template does not make it automatically approved, suitable or site-ready. It does not replace the design, manufacturer information, COSHH assessments, service controls, specialist competence, inspection or testing.
When is project-specific RAMS support useful?
Support may be useful where occupied premises, stone worktops, difficult deliveries, heavy appliances, uncertain substrates, multiple specialist connections or dust-sensitive neighbours need coordination, or where generic RAMS have been returned for revision.
For projects in Watford, Hertfordshire, London and the South East, send the approved kitchen drawings and schedule, unit and worktop details, delivery plan, substrate and service information, fixing method, stone-fabrication arrangements, access, products, programme and Principal Contractor rules. IMERI H&S Partners can then confirm an appropriate scope for project-specific RAMS support.
Official sources
This guide was checked on 30 October 2026 against the following current official sources:
- HSE: Installing stone worktops—protect against harmful natural or artificial stone dust
- HSE: Construction dust—cutting and sanding wood
- HSE: Wood dust
- HSE: Manual handling in construction
- HSE: Provision and Use of Work Equipment Regulations overview
- HSE: Electrical safety at work—frequently asked questions
This guide provides general information, not project-specific RAMS, kitchen design, a COSHH assessment, service clearance, fixing design, exposure assessment or approval of a proposed installation. Contractors and project duty holders must use current design, manufacturer and site information.