Drilling and fixing RAMS should identify exactly what will be fixed, where, into which substrate, using which drill, bit, anchor or fixing and approved installation detail. They should explain how concealed services and asbestos information will be checked, how dust, noise and vibration will be controlled, how access and falling-object risks will be managed, and how the finished installation will be inspected.
“Check for services, wear PPE and use the correct drill” is not a complete method. The document should connect the drawings and fixing specification to the actual work area, substrate, equipment, competence, sequence, quality checks and stop-work conditions.
For the wider document-control process, coordinate this task with the Construction Phase Plan and RAMS and the RAMS preparation and review guide.
Define the fixing task and its boundaries
State the item being installed, the approved location, the substrate, hole diameter and depth, fixing type, quantity, spacing, edge distance, embedment, installation tool and any specified tightening, curing, inspection or testing requirement. Take these details from the current design, product information and approved fixing schedule—not from assumption.
Distinguish routine non-structural fixings from safety-critical or structural anchors. A fixing supporting façade elements, edge protection, temporary works, lifting points, fall-arrest equipment, structural steelwork or heavy overhead services may require design, installation competence, testing and records beyond a general drilling method.
Keep the RAMS within its assessed scope. Diamond drilling, large cores, post-installed reinforcement, resin injection into unknown substrates, drilling through fire compartments, work close to live services and drilling into post-tensioned or prestressed concrete need task-specific planning and competent technical input.
What information should be obtained before drilling?
Confirm, where relevant:
- the current drawing, setting-out information, fixing schedule and manufacturer's installation instructions;
- what the fixing supports and whether it is structural, safety-critical, overhead or otherwise subject to design and testing requirements;
- the actual substrate, its thickness and condition, including voids, finishes, reinforcement, tendons, edges and existing damage;
- the approved fixing type, size, material, embedment, spacing, edge distance, hole-cleaning method, tightening or curing requirements;
- service drawings, local isolation information and the agreed method for locating electrical, water, gas, data and other concealed services;
- the asbestos register and survey information, including whether the proposed intrusion is covered by sufficiently intrusive information;
- the drill, bit, dust-control attachment, extraction unit, power supply, battery arrangement and any torque or installation tool;
- the work position, access equipment, lighting, exclusion area and protection needed below or on the opposite side of the surface;
- the material likely to be released, including silica-containing dust, asbestos risk, lead paint, coatings or other contaminants;
- expected drilling time, noise and vibration information, workforce exposure and rotation or alternative methods;
- how holes, anchors and completed fixings will be checked, recorded, tested or handed over; and
- the process for an unexpected void, service, reinforcement, weak substrate, failed hole or incorrect location.
Do not invent anchor capacities, hole-cleaning cycles, torque values, curing periods, test loads or acceptable edge distances. Use the approved design and the current manufacturer's information for the specific product, substrate and site conditions.
Write the method in the order the task will happen
A project-specific sequence may cover:
- confirming the latest drawing, approved fixing detail and work area;
- checking substrate information, asbestos information and concealed-service records;
- isolating relevant services where required and scanning or otherwise verifying the proposed drilling zone;
- marking approved positions and checking clearances, edge distances and the opposite side of the surface;
- establishing safe access, lighting, exclusion and protection from falling dust, fragments or tools;
- checking the drill, bit, guard or handle, extraction, lead or battery, and any installation tools;
- drilling with the specified diameter, depth, angle and dust controls without forcing the tool;
- stopping if the resistance, material, depth, service indication or substrate differs from the plan;
- cleaning and preparing the hole using the approved product method;
- installing and tightening or curing the fixing in accordance with the approved instructions;
- inspecting, marking and recording the fixing or completing specified testing; and
- removing dust and waste safely, protecting the installation and handing over the completed work.
Critical controls to address in drilling and fixing RAMS
Concealed services and the drilling zone
HSE warns that electrical cables may be present in walls, floors and ceilings. Review current information, inspect both sides where possible, use suitable locating equipment and establish any required isolation before drilling. A detector is an aid, not permission to drill through an unresolved indication.
Confirm the location of water, gas, data, fire-alarm, sprinkler and other services as well as electrical wiring. Stop if records, scanning and physical evidence conflict, if a service cannot be traced or if the proposed hole moves outside the checked zone.
Asbestos and existing building fabric
Before disturbing existing fabric, check that the asbestos information is adequate for the planned intrusion. HSE states that where work breaks into the building fabric, a more intrusive refurbishment survey may be required. Do not drill suspect material or an unassessed area and treat an unexpected material or damaged coating as a stop-work trigger.
Substrate, design and fixing selection
Confirm that the fixing is approved for the actual substrate and condition. Concrete, masonry, hollow block, plasterboard, steel and timber behave differently, and finishes can conceal the load-bearing material. Check whether reinforcement, tendons, edges, voids or existing holes restrict the location.
Use the specified product and installation method. Substitution can change the required hole, embedment, cleaning, setting tool, torque, curing conditions and capacity. Refer a proposed substitution or failed hole to the person responsible for the design or fixing specification before continuing.
Construction dust and hole cleaning
Drilling concrete, brick, block, mortar and other silica-containing materials can create hazardous respirable dust. Prevent or reduce drilling where possible, then use suitable on-tool extraction or another effective method matched to the task. HSE's CN3 guidance addresses drilling and coring with hand-held rotary tools, including correctly attached extraction.
Specify how dust is captured, how the extraction system is checked and maintained, and how the work area and hole are cleaned without dry sweeping or uncontrolled compressed air. Where RPE is required by the assessment, select it for the hazard and task, ensure compatibility and provide face-fit testing for tight-fitting masks.
Tool selection, condition and power
Select a drill with sufficient capacity and the correct action, bit, side handle and safety features for the task. Check the casing, chuck, bit, controls, guard where fitted, extraction connection, lead, plug, battery and charger before use. Remove damaged equipment from service and do not defeat safety devices.
Manage leads to avoid damage and trips and use the project's approved supply arrangements. Keep batteries and chargers dry, ventilated and away from combustible materials and physical damage. The tool, bit and work position should allow control without excessive force or an unstable posture.
Noise, vibration and physical control
Assess expected trigger time and exposure using reliable equipment information and the actual work pattern. HSE notes that hammer-action tools can create material vibration exposure in relatively short periods. Select lower-vibration equipment, maintain sharp effective bits, reduce unnecessary drilling, limit continuous use and provide health surveillance where the legal criteria are met.
Assess noise separately and use quieter methods, suitable equipment, segregation and hearing protection as required. Do not rely on gloves to control vibration; HSE states that they do not protect against vibration exposure.
Access, falling objects and occupied areas
Choose access equipment that allows a stable working position with controlled two-handed use where the tool requires it. Do not overreach or operate a high-torque drill from unsuitable access. Secure tools and materials where there is a falling-object risk and exclude people from the area below or behind the drilling surface.
In occupied buildings, coordinate noise, dust, service isolation, room access, alarms and protection of occupants. Confirm that drilling cannot emerge into another room, riser, ceiling void, façade or public area without appropriate control.
Resin anchors and chemical products
Where resin is used, include the current safety data and a task-specific COSHH assessment. Address storage, expiry, temperature, cartridge and nozzle condition, skin and eye contact, ventilation, waste, spill response and the manufacturer's mixing, curing and loading restrictions. Do not load or test the fixing before the specified curing condition has been achieved.
What should inspection and records cover?
Define who checks the approved location, substrate, product, hole diameter and depth, hole preparation, embedment, tightening or curing, final condition and any required marking. Where the design or specification requires proof testing, pull testing or installer records, identify the competent person, test procedure, acceptance criteria and reporting route before work starts.
Record failed or abandoned holes and obtain an approved repair or revised position. Do not conceal safety-critical fixings before the required inspection, test or record is complete. Keep product batch or installation information where the project specification requires traceability.
When should the RAMS be reviewed?
Review the method when the fixing, load, location, substrate, access, tool, dust control, service information, asbestos information, design detail or workforce changes. Also stop and reassess after an unexpected service indication, void, reinforcement strike, weak substrate, failed anchor, damaged tool, uncontrolled dust release or near miss.
Brief the affected team on the approved positions, sequence, controls, quality hold points and stop-work conditions. Principal Contractor acceptance does not transfer the contractor's duty to plan, manage and monitor the work.
When general drilling and fixing RAMS are not enough
This scope does not approve structural or safety-critical anchor design, post-installed reinforcement, lifting anchors, fall-arrest anchors, fixings into post-tensioned or prestressed concrete, large-diameter coring, diamond drilling, drilling through live services, licensed asbestos work or work on an unverified structure.
It also does not replace a COSHH assessment, asbestos survey, service-isolation procedure, temporary-works design, fixing design, fire-stopping detail, access plan or required testing regime. Obtain the relevant competent input before those activities proceed.
Can a drilling and fixing RAMS template be used?
A relevant template can provide a useful structure, but it cannot know the approved fixing position, actual substrate, concealed services, asbestos information, anchor design, tool, access or inspection requirements.
The Drilling, Anchors & General Fixings RAMS template is available in the IMERI H&S Partners RAMS shop. Check that its named scope matches the work. A competent person must assess and adapt it to the project, fixing design, substrate, services, materials, equipment, access and Principal Contractor requirements, then brief the workforce.
Buying or completing a template does not make it automatically approved, suitable or site-ready. It does not replace the current drawings, manufacturer's instructions, technical fixing design, asbestos and service information, COSHH assessment, inspection or testing.
When is project-specific RAMS support useful?
Support may be useful where several substrates or fixing systems are involved; the work is overhead, repetitive or in an occupied building; services or asbestos information require coordination; safety-critical fixings need hold points; or generic RAMS have been returned for revision.
For projects in Watford, Hertfordshire, London and the South East, send the drawings, fixing schedule, substrate information, anchor or fixing details, service and asbestos information, tools, access, testing requirements and Principal Contractor rules. IMERI H&S Partners can then confirm an appropriate scope for project-specific RAMS support.
Official sources
This guide was checked on 27 October 2026 against current HSE information:
- HSE: Construction silica and CN3 drilling guidance
- HSE: Controlling construction dust with on-tool extraction
- HSE: Electrical safety, including cables in walls, floors and ceilings
- HSE: A worker's guide to asbestos safety
- HSE: Provision and Use of Work Equipment Regulations overview
- HSE: Construction vibration risks and controls
This guide provides general information, not project-specific RAMS, fixing or structural design, an asbestos survey, COSHH assessment, service clearance, test specification or approval of a proposed installation. Contractors and project duty holders must use current design, product, building and site information.