RAMS · Low-level access · Work at height

Stepladders and podium steps RAMS: what contractors should include.

Low-level work still creates a fall risk. This guide explains what contractors should establish before choosing, setting up and using stepladders or podium steps for routine construction tasks.

Stepladder and podium-step RAMS should define the task, location, working height and duration; justify the selected access equipment; identify the exact equipment and manufacturer's instructions; confirm competent users and supervision; set out delivery, pre-use checks and stable setup; control overreaching, side loading, tools, materials, people below and nearby activity; and state when the work must stop or be reassessed.

HSE says ladders and stepladders can be a sensible option for low-risk, short-duration work, but they should not automatically be the first choice. The Work at Height Regulations require work at height to be avoided where reasonably practicable and collective protection to take priority when equipment is selected.

A guarded podium may provide a larger platform and greater collective protection than an ordinary stepladder for some tasks. That does not make every podium suitable for every job. Platform dimensions, guardrails or gates, access, stabilisers, castors, safe working load and permissible use vary by product, so the RAMS must follow the actual manufacturer's instructions.

Choose the equipment for the task—not just the height

Start with what the person must do: the work position, reach, force, duration, frequency, tools, materials and whether one or both hands are needed. Also consider the floor, doors, vehicles, pedestrians, edges, openings, overhead services, changes in level and the route used to bring equipment into the area.

For a stepladder, the risk assessment should establish that equipment offering a higher level of fall protection is not justified because the work is low risk and short duration, or because fixed workplace features cannot be altered. HSE uses 30 minutes at a time as a guide for considering alternative equipment, but duration alone does not justify ladder use.

Where repeated work, two-handed work, side loading, difficult reach, heavier tools or materials, or a larger working area is involved, a podium, mobile tower, MEWP or another suitable platform may be the better choice. The RAMS should record the decision for the real task and setting.

What information should be available before work starts?

Confirm, where relevant:

  • the task, workface, required reach, working height, duration, frequency and number of users;
  • the tools and materials to be handled, their weight, and whether the task produces side loading or requires two hands;
  • the selected stepladder or podium make, model, configuration, safe working load and current user instructions;
  • who will select, check, set up, use, supervise and remove the equipment, and the evidence supporting their competence;
  • the floor condition, level, strength, cleanliness and any holes, covers, edges, steps, slopes or temporary finishes;
  • nearby doors, windows, vehicles, pedestrians, members of the public, overhead electrical conductors and other work;
  • podium-specific gates, guardrails, stabilisers, locking devices and castor arrangements;
  • delivery, carrying, storage and defect-isolation arrangements;
  • the required exclusion, barriers, lighting and housekeeping; and
  • the stop-work and review triggers if the task, equipment, workface, floor or surrounding activity changes.

Do not describe equipment merely as steps or access tower. Record enough information to confirm that the chosen product can be used in the proposed configuration and that the user instructions and limits will be available at the workface.

Write the method in the order the work will happen

A proportionate sequence may cover:

  1. reviewing whether the work can be completed from ground level and selecting suitable access equipment under the work-at-height hierarchy;
  2. confirming the task, users, location, equipment, instructions, load and local site requirements;
  3. moving the equipment to the work area without damage or uncontrolled manual handling;
  4. isolating the area and checking the floor, overhead hazards, lighting and nearby activity;
  5. completing the pre-use check and removing defective or unsuitable equipment from service;
  6. opening and setting the equipment in the manufacturer's permitted configuration, with all locks, gates, stabilisers and castors correctly engaged;
  7. briefing the user on access, handholds, work position, reach, tools, materials and exclusion requirements;
  8. carrying out the task without overreaching, improvising extra height or moving occupied equipment;
  9. stopping for a defect, impact, contamination, unstable surface, changed task or uncontrolled interface; and
  10. closing the area, cleaning and checking the equipment, and storing it securely.

Critical controls to address in low-level access RAMS

Competence and instructions

Anyone organising, planning, supervising or carrying out work at height must be competent, or supervised while being trained. The user should understand when the equipment is suitable, how it is checked and set up, the permitted steps or platform, the load limit, and the defects or conditions that take it out of use.

Keep the manufacturer's instructions available. Do not assume different podiums have the same locking, stabiliser, gate, castor or platform arrangements, or that a stepladder can be used in a configuration not shown on its label.

Stable, clean and protected setup

Use a firm, level, clean surface that can support the equipment, user, tools and materials. HSE advises against ad-hoc packing such as bricks, blocks or timber. Check that stepladder feet are in full contact and steps are level; engage spreaders and other locking devices.

For a podium, apply every brake, lock, stabiliser, gate and guardrail required by its instructions before access. Never move occupied equipment. Protect the setup from doors, vehicles, mobile plant, pedestrians and other trades, and prevent people from passing through the work zone where tools or materials could fall.

Safe work position and three points of contact

HSE says a stepladder user should maintain three points of contact at the working position: normally two feet and one hand, or—during a brief period of light work—two feet and the body supported by the stepladder. Keep the body between the stiles, avoid overreaching and reposition the equipment instead.

Do not stand and work on the top three steps, including a top step, unless a suitable handhold is provided. Avoid side-on drilling or other force that could overturn the stepladder. Where side loading cannot be controlled as HSE describes, choose more suitable access equipment.

Tools, materials and the area below

Only carry light tools and materials that can be handled while maintaining safe support and the equipment's load limit. Use suitable tool belts, holders or another controlled method where appropriate. Do not place loose items on guardrails, gates or steps, or leave them where they can fall.

Set the exclusion to suit the task, item and occupancy below. A small cone beside a stepladder does not control a busy corridor, opening door or vehicle route. Coordinate with the Principal Contractor where access affects escape routes, other trades, public areas or occupied premises.

No improvised height or unauthorised alteration

Do not stand equipment on pallets, blocks, trestles, scaffold platforms or other objects to gain height. Do not climb podium guardrails, work from an open gate, remove components, or use an improvised plank between access units. Select different equipment when the work cannot be reached from the permitted work position.

What should checks and inspections cover?

HSE says the person using a ladder should complete a pre-use check at the start of the working day and after a change that could affect its condition, such as being dropped or moved between dirty and clean surfaces. For a stepladder, check the stiles, feet, steps, treads, platform, hinges, fixings and locking mechanisms, including contamination or damage.

For podium steps, use the manufacturer's checklist and inspect the frame, steps, platform, guardrails, gate, braces, stabilisers, castors, brakes, welds, fixings and identification. The exact inspection and record requirements depend on the equipment, how its safety depends on assembly or installation, its exposure to deterioration and the applicable instructions.

Tagging can help communicate status but does not replace a competent check, inspection or defect process. Remove defective equipment from the work area, identify it clearly, prevent reuse and arrange repair only through an appropriate authorised route.

When low-level access RAMS are not enough

Reassess the equipment where the work is prolonged, frequent, high-force, outside, beside an edge or opening, close to live conductors, above the public, on stairs or uneven ground, or dependent on carrying bulky or heavy materials. Also reassess where a person cannot work from the permitted position without leaning, twisting or using both hands for more than a brief light task.

This scope does not cover leaning ladders used for access, roof ladders, fixed ladders, mobile towers, system scaffolds, trestles, MEWPs, fall-arrest systems or improvised platforms. Each has different planning, competence, equipment and rescue considerations.

Can a stepladder and podium-step RAMS template be used?

A template can provide a controlled structure for routine low-level access. It cannot decide whether work at height is necessary, select the equipment, verify the work surface, confirm competence, or inspect the stepladder or podium.

The Stepladders & Podium Steps – Low-Level Access RAMS template is available in the IMERI H&S Partners RAMS shop. Check its named scope before purchase and use. A competent person must assess and adapt it to the actual task, equipment instructions, site conditions and Principal Contractor arrangements, then brief the workforce. Buying or completing a template does not make it automatically approved, suitable or site-ready.

Coordinate access arrangements with the Construction Phase Plan and task RAMS, and use the RAMS preparation and review guide to keep ownership and change control clear.

When project-specific support is useful

Support is useful where repeated low-level work involves several rooms or trades; the site is occupied; equipment is used beside traffic, doors, openings or the public; the work requires two hands or creates side loading; or the Principal Contractor has returned generic access arrangements for revision.

For projects in Watford, Hertfordshire, London and the South East, send the task, working height, duration, access equipment details, floor conditions, tools and materials, work area, workforce and Principal Contractor requirements. IMERI H&S Partners can then confirm an appropriate scope for project-specific RAMS support.

Official sources

This guide was checked on 25 October 2026 against current HSE and legislation.gov.uk information:

Need project-specific low-level access RAMS?

Start with the task, equipment and work area.

Send the task, working height, duration, access equipment details, floor conditions, tools and materials, work area and Principal Contractor requirements for a proportionate RAMS quotation.