Manual-handling RAMS should identify the actual load, handling task, origin and destination, route, frequency, posture, lifting or moving aids, storage arrangements, people involved and foreseeable changes. They should show how hazardous handling will first be avoided where reasonably practicable, how unavoidable work has been assessed and how the remaining risk will be reduced.
Manual handling includes lifting, putting down, pushing, pulling, carrying or otherwise moving a load by hand or bodily force. The method must cover the whole movement, including collecting, gripping, crossing thresholds or stairs, placing, stacking and any repositioning—not only the moment the load leaves the ground.
Where materials arrive by vehicle, coordinate the task with the delivery, unloading and distribution arrangements. The task method should also align with the Construction Phase Plan, logistics plan, storage layout and Principal Contractor's rules.
Start with the legal hierarchy: avoid, assess and reduce
Regulation 4 of the Manual Handling Operations Regulations 1992 requires employers, so far as reasonably practicable, to avoid manual handling operations that involve a risk of injury. Where they cannot be avoided, the employer must make a suitable and sufficient assessment and reduce the risk to the lowest level reasonably practicable.
That order matters. Do not begin with lifting technique or personal protective equipment. First consider design, procurement, packaging, prefabrication, delivery location, storage, mechanical handling and work sequencing. If people still need to handle materials, assess the remaining operation and select proportionate controls.
Use competent judgement and consult the workers who do the task. HSE's MAC tool may help identify higher-risk lifting, carrying and team-handling tasks; the RAPP tool addresses pushing and pulling. These tools support assessment but do not replace project information or create automatic pass/fail weight limits.
What information should be obtained before work starts?
Confirm, where relevant:
- the material, unit weight, dimensions, shape, packaging, stability, grip points and centre of gravity;
- whether it may be sharp, hot, wet, slippery, fragile, dusty, contaminated or liable to move unexpectedly;
- the number of units, handling frequency, duration, work rate and realistic rest or rotation arrangements;
- the collection point, final position, carry distance, height changes, stairs, thresholds, doors, slopes and turning space;
- the condition and lighting of the route, including obstructions, uneven or slippery surfaces, excavations, edges and other trades;
- whether the load can be eliminated, reduced, split, supplied in a different form or delivered closer to its point of use;
- the crane, hoist, telehandler, pallet truck, trolley, sack barrow, material lift, vacuum lifter, grip or other aid available;
- the suitability, capacity, condition and planned use of each aid, including space to operate and maintain it;
- the people involved, including relevant capability, experience, instruction and any known factors that may increase risk;
- the storage height and arrangement, stable stacking method, floor loading and access needed for later retrieval; and
- the stop-work, defect, dropped-load, first-aid and reporting arrangements.
Where there is a risk of injury, provide general indications of load weight and, where reasonably practicable, precise information on the weight and on the heaviest side where the centre of gravity is off-centre. Do not expect workers to discover an awkward or unbalanced load during the lift.
Write the method in the order the handling will happen
A project-specific sequence may cover:
- confirming the material, weight, condition, route, destination and assessed handling method;
- removing unnecessary handling through mechanical placement or delivery closer to the workface;
- checking that the route, storage area, lifting aid and receiving position are ready;
- briefing roles, communication, individual handling limits and stop conditions;
- checking the load and packaging before gripping, tilting or releasing it;
- using the planned aid or team arrangement without creating trapping, overturning or collision risks;
- lifting, carrying, pushing or pulling along the cleared route at the assessed rate;
- placing the load in a stable position without uncontrolled lowering, reaching or finger trapping;
- removing packaging and waste without creating a new obstruction; and
- reporting defects, symptoms, near misses or changes before the task continues.
Critical controls to address in manual-handling RAMS
Design, procurement and logistics
Reduce physical handling through prefabrication, mechanical placement, smaller or lighter units, better grip points, suitable packaging and delivery close to the point of use. Keep materials dry where water would increase weight or reduce grip. Plan distribution while cranes, telehandlers, goods lifts or pallet trucks can still reach the work area.
Task, load, environment and individual capability
Assess the combined operation rather than judging weight alone. Consider holding the load away from the body, twisting, stooping, reaching, high or low placement, long carries, repetition, sudden movement and time pressure. For the load, consider bulk, shape, stability, visibility, grip and harmful surfaces or contents.
Assess the route and workplace: restricted posture, stairs, changes in level, wind, temperature, lighting, uneven or slippery ground, clothing or PPE restrictions and interaction with vehicles or other trades. Take account of individual capability and known factors that may increase risk; do not assume that training or previous experience makes a poorly designed task acceptable.
Lifting and moving aids
Select an aid that fits the material, route and destination. A trolley with small wheels may be unsuitable on rough ground; a pallet truck needs a suitable surface and space; a grip device must match the product. Inspect aids before use, maintain them and keep wheels, brakes, handles and restraints in serviceable condition.
Mechanical assistance can introduce vehicle, lifting, crushing or overturning hazards. Where the task involves cranes, hoists, telehandlers or other lifting equipment, the separate planning, competence, examination and supervision requirements still apply. Manual-handling RAMS do not replace a lift plan.
Team handling
Team handling is not an automatic solution for a load that is too heavy, bulky or unstable for one person. The team must have space, compatible capability, a common route and a clear view or communication method. Nominate the person who controls the movement and agree when to lift, turn, stop and lower. Reassess if the load prevents coordinated posture or exposes one person to a disproportionate share.
Pushing, pulling and final positioning
Assess starting and stopping forces, the height and condition of handles, wheel condition, slope, surface, direction changes and the risk of a runaway or trapped person. Wherever possible, push with a clear view rather than pull while walking backwards. Control doors, ramps, thresholds and gradients and keep hands and feet away from trapping points when placing the load.
Technique, information and supervision
Good handling technique is an addition to physical and organisational controls, not a substitute for them. The briefing should be specific to the task and cover the planned grip, route, aid, posture, pace, communication, set-down point and stop conditions. Workers should know the load information and be able to pause if the material, route or their ability to control it differs from the assessment.
Is there a universal safe lifting weight?
No. HSE states that the law does not set specific maximum weight limits, and its risk-filter figures are not safe limits. Risk depends on the complete task: position, reach, frequency, distance, grip, load stability, route, environment and the person doing the work.
A lighter item can still present significant risk when it is repeated, carried far, handled above shoulder height, taken down stairs or controlled in a restricted space. A stated load weight is useful information, but it cannot by itself approve the task or replace a suitable and sufficient assessment.
How should the RAMS be briefed and reviewed?
Brief the people who receive, distribute, move and place the materials. They should understand the load, route, selected aids, roles, pace, communication, stable storage, symptoms or defects to report and the conditions that require work to stop.
Review the assessment where there is reason to suspect it is no longer valid or the operation changes significantly. Practical triggers include different product sizes or weights, damaged packaging, loss of a lifting aid, a longer or obstructed route, changed access, wet or uneven ground, new work at height, increased frequency, fewer people, symptoms or a near miss. Pause, revise and re-brief before continuing.
When routine manual-handling RAMS are not enough
This scope does not cover complex lifting operations, crane or hoist planning, lifting people, rescue, mechanically suspended loads, abnormal or shifted loads, live services, hazardous substances, demolition, unstable structures or the design and capacity of floors, racks or temporary works. It also does not cover patient or animal handling.
Obtain the relevant specialist planning and competent input where the load, equipment, structure or interface demands it. Do not extend a routine handling method to justify an improvised lift, an unverified structure or equipment being used outside its instructions.
Can a manual-handling RAMS template be used?
A relevant template can provide a controlled structure, but it cannot know the actual load, route, frequency, workforce, work rate, lifting aids, storage plan or site interfaces.
The Manual Handling of Construction Materials RAMS template is available in the IMERI H&S Partners RAMS shop. Check that its named scope matches the planned activity. A competent person must assess and adapt it to the project, materials, route, equipment, workforce and Principal Contractor requirements, then brief the people doing the work.
Buying or completing a template does not make it automatically approved, suitable or site-ready. It does not replace supplier information, a manual-handling assessment, lifting arrangements, structural confirmation, site rules or competent review.
Use the RAMS preparation and review guide to keep ownership clear, and coordinate the task method with the Construction Phase Plan and RAMS.
When is project-specific RAMS support useful?
Support may be useful where heavy, bulky or unstable products are handled repeatedly; routes include stairs, occupied areas or uneven ground; lifting aids and several trades must be coordinated; the workforce or task changes; or a Principal Contractor has returned a generic assessment for revision.
For projects in Watford, Hertfordshire, London and the South East, send the material schedule, load weights and sizes, delivery and storage plan, handling route, lifting aids, workforce information and Principal Contractor requirements. IMERI H&S Partners can then confirm an appropriate scope for project-specific RAMS support.
Official sources
This guide was checked on 26 October 2026 against current HSE and legislation.gov.uk information:
- The Manual Handling Operations Regulations 1992, Regulation 4
- HSE: Manual handling at work
- HSE: Construction physical ill health risks—manual handling
- HSE: Assess manual handling you cannot avoid
- HSE: Simple manual-handling risk filters
- HSE: Good handling technique
This guide provides general information, not project-specific RAMS, a lift plan, structural assessment or approval of a proposed operation. Employers, contractors and project duty holders must assess the actual task and use current product, equipment, workplace and project information.