Door & ironmongery installation RAMS: what contractors should include.

A workable method should connect the door schedule, opening, complete doorset or door assembly, hardware, handling plan, fixings, tools, access and acceptance checks to each location—not treat every door as the same task.

Door and ironmongery installation RAMS should establish that the correct door, frame, hardware, opening, fixings, access and handling arrangements are available before installation begins. They should then explain how each assembly will be moved, supported, fitted, adjusted, tested, protected and handed over without unsafe substitution or uncontrolled modification.

“Hang the door and fit the ironmongery” is not a complete method. The document should identify the actual door schedule and locations, leaf weights and sizes, frame or lining, hardware set, opening and substrate, fixing specification, survey information, delivery route, tools, access equipment, powered interfaces, inspection criteria and stop-work conditions.

Coordinate the method with the carpentry and joinery RAMS guide, the drilling and fixings guide, the manual-handling guide and the project's Construction Phase Plan.

Define the installation task and its boundaries

State the rooms, plots and door references included and whether the work covers delivery, storage, existing-door removal, frames or linings, door leaves, hinges, locks, latches, handles, closers, panic or emergency hardware, seals, thresholds, stops, guards, signage, access-control interfaces, adjustment, testing, protection and waste removal.

Identify whether the item is an ordinary internal door, external door, entrance doorset, security door, acoustic assembly or specified fire-resisting doorset. These descriptions are not interchangeable. The approved schedule, specification and manufacturer or test evidence should define the components, permissible preparation, fixings, gaps and hardware—not an assumption based on appearance.

Structural alteration, door or fire-strategy design, powered access-control connection, glazing outside the installer's competence, asbestos work, lifting operations outside the assessed method and repairs that change the tested or specified assembly need their own information, competence and controls.

What information should be obtained before installation?

Confirm, where relevant:

  • the current door schedule, drawings, specification, room and door numbers, handing and opening direction;
  • the complete door or doorset reference, leaf material, dimensions, weight, frame, seals, glazing, threshold and finish;
  • the ironmongery schedule, approved hardware set, fixing positions, templates and manufacturer instructions;
  • the wall or partition build-up, opening dimensions, substrate, tolerance, fixing zones and approved fixing detail;
  • the design or test evidence governing any specified fire-resisting, smoke-control, security, acoustic or emergency-exit function;
  • asbestos information for existing door leaves, fire-protection panels, linings, reveals and surrounding construction that may be disturbed;
  • concealed electrical, access-control, alarm or other services near drilling, chasing or fixing locations and the isolation arrangements;
  • door, frame and hardware delivery sequence, storage conditions, weights, handling aids and route to the workface;
  • cutting, routing, drilling and fixing tools, extraction, electrical supply, access equipment and operator competence;
  • occupied-area controls, temporary security, escape-route and other-trade interfaces; and
  • hold points for opening acceptance, first-off installation, fixing, gaps, hardware, functional testing and handover.

Write the method in the order the work will happen

A project-specific sequence may cover:

  1. confirming the latest schedule, door reference, handing, component set, location, survey scope and responsibilities;
  2. checking the opening, substrate, dimensions, tolerances, fixing zones, access and surrounding finishes;
  3. receiving and inspecting the doors, frames and hardware against the schedule before controlled storage;
  4. planning the route and moving each load with the selected handling aid and enough space for safe control;
  5. removing an existing assembly only where the survey, isolation and temporary-security arrangements permit it;
  6. positioning and temporarily supporting the frame or lining before the specified packers and fixings are installed;
  7. supporting and hanging the leaf without relying on an unsecured frame or exposing hands to pinch points;
  8. marking and preparing only the approved hinge, lock, closer and hardware locations with controlled tools and dust extraction;
  9. fitting the specified hardware, seals, thresholds, guards and interfaces without unapproved substitution;
  10. checking gaps, clearances, swing, closing, latching, locking, emergency operation and surrounding finishes;
  11. recording defects and corrective work, then protecting the assembly from damage or misuse; and
  12. handing over only after the authorised inspection and functional checks are complete.

Critical controls to address in door-installation RAMS

Door weights, delivery and manual handling

Obtain the dimensions and weight of each leaf, frame and packaged assembly rather than estimating by door type. Doors are large, awkward to grip, liable to catch wind and can obstruct the carrier's view. Check stairs, turns, thresholds, floor condition, lighting, temporary edges and the final setting-down area.

Use suitable trolleys, door lifters, carriers or other handling aids where the assessment requires them. Deliver close to the point of use, keep packs stable and protect stored doors from toppling. Team handling and technique training can support a planned operation, but do not replace avoiding, reducing or mechanising a high-risk lift.

Existing doors, asbestos and concealed services

Asbestos insulating board can be concealed inside older fire doors or present in adjacent panels and reveals. Before cutting, drilling, sanding or removing an existing assembly, confirm that suitable asbestos information covers the precise material and depth of disturbance. Stop, prevent further disturbance and escalate if suspect material or an unsurveyed layer is found. Routine door-installation RAMS do not authorise asbestos work.

Confirm service information and inspect the proposed fixing locations. Isolate relevant electrical or powered access-control systems where the work could disturb them. Do not rely on drawings alone or proceed through an uncertain wall, head or floor detail. Stop for unexpected cables, pipes, voids, reinforcement or a substrate that differs from the approved information.

Frames, leaves and temporary stability

Define how frames, linings and leaves will be supported while set, packed and fixed. Keep the area controlled until the assembly is stable and do not leave a heavy leaf leaning unsecured. Use the approved fixing type, quantity, spacing, edge distance and substrate condition; do not substitute fixings or improvise packers because the scheduled item does not fit.

Control fingers and hands at hinges, closing edges, under leaves and between the frame and opening. Use positioning aids and an agreed communication method when more than one person controls the load. Restrain or remove a door closer's stored energy using the manufacturer's safe method before adjustment or removal.

Tools, wood dust and sharp components

Select drills, routers, saws, planers, chisels, morticers and fixing tools for the material and operation. Inspect guards, cutters, bits, leads and extraction; secure the workpiece; isolate equipment before adjustments or blade changes; and keep sharp tools and loose ironmongery controlled.

Powered cutting, routing and sanding can generate significant wood dust. Order factory-prepared doors and frames where practicable and limit site machining to the approved preparation. Use suitable on-tool extraction connected to an appropriate vacuum, maintain effective airflow and use vacuum cleanup rather than dry sweeping or compressed air. Select and face-fit tight-fitting RPE where the assessment requires it.

Assess exposure where hammer drills, routers, sanders or other vibrating tools will be used repeatedly. Reduce trigger time through the method and tool choice, maintain equipment, avoid excessive force and apply any required health-surveillance arrangements.

Access for closers, head details and high-level hardware

Select access equipment from the task, height, duration, required force and materials. A ladder or stepladder may be suitable only for low-risk, light work of short duration where a higher-protection option is not justified. Use a suitable platform where the task needs two-handed force, side loading, repeated drilling or longer duration.

Keep three points of contact where ladder use requires it, prevent doors or people from striking the equipment and segregate the area below. Do not use the newly hung leaf, frame, loose pack or improvised surface as access.

Occupied areas, escape routes and powered interfaces

Plan temporary security and safe access before an existing door is removed. Maintain required escape routes or agree and communicate the authorised temporary arrangement. Separate building users and other trades from exposed openings, swinging leaves, sharp hardware, trailing leads and incomplete thresholds.

Access-control cabling, electromagnetic locks, powered operators and alarm interfaces should be connected, isolated and commissioned by people competent for that system. The door installer's method should define the interface and release point rather than imply that carpentry RAMS authorise live electrical work or system design.

How should specified fire-resisting doorsets be addressed?

For work in England, current GOV.UK guidance describes a fire doorset as the complete installed assembly: the door, frame and ironmongery are considered together. The project-specific method should therefore follow the approved schedule, relevant evidence and manufacturer's installation instructions for that exact assembly.

Confirm the permitted frame, hardware, seals, glazing, fixings, gaps and preparation before work starts. Do not plane, drill, route, trim, substitute or omit a component merely to resolve a site mismatch. Record the mismatch, protect the opening and obtain the authorised design or manufacturer response.

This guide and IMERI H&S Partners' routine RAMS support do not market or provide fire-door inspection services. The installer remains responsible for following the approved information and the project must retain any separate design, certification, inspection or responsible-person arrangements that apply.

What should hold points and records cover?

Identify who accepts the opening, substrate, component set, fixing detail, first-off installation and any repair or deviation. Record door and location references, batch or identification details where required, concealed fixings before they are covered and the approved response to defects.

Final checks should address level and plumb, gaps and clearances, secure fixings, hinge operation, swing, closing, latching, locking, seals, thresholds, closers, emergency hardware, access-control interface, sharp edges, damage and protection. Use the scheduled function and manufacturer or project criteria; a door that moves is not necessarily an accepted assembly.

When should the RAMS be reviewed?

Review the method when the door reference, weight, opening, substrate, fixing, hardware set, design evidence, survey, service information, access, tool, route, occupancy or programme changes. Stop and reassess after finding suspect material, concealed services, an out-of-tolerance opening, damaged component, incompatible hardware, unapproved preparation, unstable support or a near miss.

Brief the team on the approved schedule, handling plan, component restrictions, tool and dust controls, access arrangement, hold points and stop-work conditions. Principal Contractor acceptance does not make a generic document suitable or transfer the contractor's duty to plan, manage and monitor the work under its control.

When routine door-installation RAMS are not enough

This scope does not approve structural alteration, doorset or fire-strategy design, fire-door inspection, asbestos work, live electrical work, powered-system design, glazing outside the installer's competence, specialist lifting outside the assessed method or an unapproved change to a tested or specified assembly.

It also does not replace the door and ironmongery schedules, design and test evidence, asbestos information, service survey, fixing specification, manufacturer instructions, COSHH assessment, competence requirements, access plan, inspection plan or handover records.

Can a door-installation RAMS template be used?

A relevant template can provide a useful structure, but it cannot know the door schedule, leaf weights, openings, substrates, hardware sets, survey findings, fixing details, access-control interfaces, delivery route, workforce or project acceptance requirements.

The Door & Ironmongery Installation RAMS template is available in the IMERI H&S Partners RAMS shop. Check that its named scope matches the work. A competent person must assess and adapt it to the project, schedules, surveys, components, tools, access, workforce and Principal Contractor requirements, then brief the workforce.

Buying or completing a template does not make it automatically approved, suitable or site-ready. It does not replace manufacturer instructions, design information, competent installation, inspection, testing or handover.

When is project-specific RAMS support useful?

Support may be useful where doors are heavy or numerous, several hardware sets are involved, existing assemblies are being removed, premises remain occupied, powered access control must be coordinated, or generic RAMS have been returned for revision.

For projects in Watford, Hertfordshire, London and the South East, send the door and ironmongery schedules, drawings, leaf weights, opening and substrate information, survey and service details, fixing specification, tools, access arrangements, programme and Principal Contractor rules. IMERI H&S Partners can then confirm an appropriate scope for project-specific RAMS support.

Official sources

This guide was checked on 2 November 2026 against the following current official sources: