RAMS · Carpentry · Joinery installation

Carpentry and joinery RAMS: what contractors should include.

Good carpentry RAMS describe the actual components, installation sequence, tools, cutting arrangements, fixings and work area. This guide explains what contractors should establish before routine first-fix or second-fix joinery begins.

Carpentry and joinery RAMS should identify the drawings and specification, components and weights, cutting and assembly method, tools and fixings, competent installers, access, interfaces and controls for blades, projectiles, wood dust, noise, vibration, handling and other people. They should explain the work in installation order, identify hold points and state what changes require work to stop.

Under CDM 2015, contractors must plan, manage and monitor the work under their control and consider risks to anyone affected by it. That requires more than a generic list of tools and PPE: the method must be connected to the actual joinery package, work area and project arrangements.

The RAMS should align with the Construction Phase Plan and project-wide arrangements, approved drawings, material information, COSHH assessments, service information, access plan, fire precautions and Principal Contractor rules.

Define the work and its boundaries

State whether the work covers first-fix timber framing, noggins and grounds; second-fix skirtings, architraves and trims; standard internal joinery; or another clearly described package. Identify the rooms or plots, drawing revisions, materials, finishes, tolerances, fixing substrates and interfaces with drylining, mechanical and electrical services, decorations and flooring.

Separate manufacture from site installation. A method for fitting prepared joinery is not automatically suitable for workshop production, fixed woodworking machinery or extensive on-site machining. Confirm which components arrive pre-cut or pre-finished and which adjustments are permitted on site.

Keep the RAMS within its assessed limits. Routine installation RAMS should not be extended to structural timber frames or roof trusses, formwork, fire-door certification or inspection, large glazed joinery, heavy or powered doors, façade work, live electrical work, asbestos disturbance or specialist workshop machinery. Those activities need different or additional competent planning.

What information should be obtained before work starts?

Confirm, where relevant:

  • the latest drawings, schedules, specifications, samples, tolerances and installation instructions;
  • the component type, dimensions, weight, finish, moisture or storage requirements and any fragile, sharp or awkward features;
  • the delivery, unloading, storage and distribution route, including floor loading and protection requirements;
  • the substrate, permitted fixing zones, fixing type, edge distances, embedment and manufacturer information;
  • the location of electrical, water, gas and other concealed services before drilling, screwing or nailing;
  • the building age, asbestos register or survey and whether the work will disturb existing fabric;
  • the saws, drills, routers, planers, sanders, nail guns and hand tools proposed, with guards, extraction and inspection arrangements;
  • the cutting station, support benches, workpiece restraint, lighting, power supply and exclusion arrangements;
  • wood species and sheet materials, adhesives, sealants, fillers, preservatives and finishes, with relevant COSHH information;
  • the access equipment, working height, duration and need to handle materials while positioned at height;
  • noise and vibration information, expected trigger time and exposure from other tools; and
  • quality checks, fire-stopping or service interfaces, protection, waste removal and handover requirements.

Do not invent component weights, fixing capacities, dust-control performance, exposure times or acceptable tolerances. Obtain them from the design, supplier information, tool data, actual assessment and project requirements.

Write the method in the order the work will happen

A project-specific sequence may cover:

  1. confirming the work area, latest drawings, components, substrates, services and authority to proceed;
  2. checking that preceding works, openings, supports, levels and environmental conditions are ready;
  3. planning delivery, storage and distribution so joinery remains stable, protected and accessible;
  4. setting up a controlled cutting area with suitable benches, lighting, power and dust extraction;
  5. inspecting tools, guards, blades, bits, batteries, leads and extraction equipment before use;
  6. measuring, marking and checking the component before cutting or drilling;
  7. supporting and restraining the workpiece and making permitted cuts with the selected tool;
  8. offering up, packing, plumbing, levelling and temporarily supporting the component as required;
  9. checking the substrate and service information before drilling, nailing or fixing;
  10. installing the specified fixings and completing the defined quality hold point;
  11. applying specified sealants, fillers or finishes under the relevant COSHH controls; and
  12. protecting the finished work, cleaning with suitable dust-control methods and handing over the area.

Critical controls to address in carpentry and joinery RAMS

Competence, drawings and permitted adjustments

Identify who supervises the package and who is competent to use each powered tool. Installers should understand the drawing, schedule, specified fixing and manufacturer information as well as the safe method. If the component, opening or substrate differs from the approved information, stop and obtain instruction rather than cutting or packing until it fits.

Define quality hold points where errors could create a safety problem—for example before concealing fixings, closing service zones or accepting supports. RAMS should not authorise unapproved structural alterations or changes to fire-resisting construction.

Delivery, storage and manual handling

Plan how timber, sheet materials and joinery will move from delivery point to workface. Assess the task, load, environment and individual capability for handling that cannot be avoided. Use mechanical aids, smaller loads, team handling or revised routes where they reduce risk; handling technique alone is not the first control.

Store long lengths and sheet materials on suitable level supports so they cannot slip, bow, topple or obstruct routes. Protect finished edges and glazing where applicable. Do not lean unstable stacks against walls or leave protruding materials where they create impact or trip hazards.

Cutting stations, blades and portable tools

Use the right saw or tool for the material and cut. Provide a stable bench, effective workpiece support and restraint, suitable guarding and enough clearance for the component and offcut. Keep hands outside the cutting path and use manufacturer-provided push devices or guides where required. Isolate tools before blade or bit changes, adjustment, clearing a blockage or investigating a fault.

Check guards, riving knives or other safety devices where fitted, as well as blades, bits, switches, leads, plugs, batteries and extraction connections. Do not defeat guards, improvise accessories or use a damaged, blunt or unsuitable blade. Fixed woodworking machinery requires machine-specific controls and competent use; a general portable-tool section is not enough.

Nail guns, fixings and concealed services

Where a nail gun is used, specify the correct tool, fastener and operating mode for the work. HSE warns that nails can be deflected and that splinters or dust can be ejected. Keep the free hand and other people out of the firing line, never carry the tool with a finger on the trigger and do not defeat safety features. Isolate the energy source before clearing a jam or carrying out maintenance.

Confirm fixing zones and concealed services before drilling, screwing or nailing into existing construction. Use drawings, surveys and suitable locating arrangements as required by the task. Stop where the substrate is unknown, a service is indicated or the proposed fixing could damage fire protection, waterproofing, structure or another completed system.

Wood dust, composites and hazardous products

Cutting and sanding wood with power tools can create significant dust. Hardwood, softwood and composite-board dust must be assessed; ordering pre-cut materials and using a dedicated cutting area can reduce exposure and spread. Use effective on-tool extraction or suitable local exhaust ventilation for the task and clean with an appropriate vacuum rather than dry sweeping or compressed air.

RPE is additional protection, not a substitute for controlling dust at source. Where tight-fitting RPE is required it must be suitable, compatible with other PPE and face-fit tested. Consider health surveillance where the assessment identifies a continuing risk such as occupational asthma or dermatitis. Adhesives, sealants, fillers, preservatives and finishes require a task-specific COSHH assessment based on how they will actually be used.

Noise, vibration, electricity and housekeeping

Assess noise and hand-arm vibration using suitable information for the actual tools, materials and duration. Consider combined daily exposure from all tools. Select lower-noise and lower-vibration options where reasonably practicable, maintain equipment, organise work to reduce exposure and provide health surveillance where required by the assessment.

Use a suitable power supply and protect leads from damage, water, vehicles and trip hazards. Battery charging needs a suitable location and manufacturer-approved equipment. Remove offcuts, sharp fasteners and packaging progressively; do not let dust or waste obscure the floor or block escape routes.

Access, work at height and protection of others

Select access equipment from the task and risk, not convenience. HSE permits ladders and stepladders where the assessment shows that higher-protection equipment is not justified because the task is low risk and short duration, or because existing features cannot be altered. Repetitive fixing, forceful work, long-duration work or handling awkward materials may require podiums, towers or another suitable platform.

Keep access equipment level, stable and inspected. Avoid overreaching and do not climb while carrying a component that prevents safe contact. Establish an exclusion area where cutting, overhead fixing, nail-gun use or falling offcuts could affect other workers, occupants or the public.

Existing buildings, fire precautions and change

Before disturbing existing fabric, check that asbestos information is sufficient for the work. A refurbishment survey may be required where the work will break into material that could conceal asbestos. Stop if suspect material, unexpected insulation or unidentified board is found.

Control timber waste, dust, flammable products and battery charging within the project fire arrangements. State how to respond to blade contact, nail penetration, eye injury, dust-control failure, electric shock, service strike, fire and material collapse. Give installers authority to stop when the component, substrate, drawing, tool, fixing, access or work area differs from the assessment.

How should the RAMS be briefed and reviewed?

Brief the supervisor, installers and people controlling adjacent areas. They should understand the component and drawing, permitted adjustments, handling route, cutting station, selected tools, dust controls, fixing zones, access method, exclusion arrangements, quality hold points and emergency actions. Confirm understanding rather than relying on a signature alone.

Review the RAMS if drawings, components, materials, substrates, fixings, tools, cutting location, access, service information, programme or nearby activities change. A substitution that appears minor can alter weight, dust, fixing, fire or handling risks.

The contractor retains responsibility for planning and safely carrying out its work. Principal Contractor review, a permit or an accepted RAMS document does not transfer that duty.

Can a carpentry and joinery RAMS template be used?

A relevant template can provide a useful structure, but it cannot know the actual drawings, components, weights, substrates, service zones, tools, access, materials or project rules.

The IMERI H&S Partners Carpentry & Joinery Installation RAMS template is currently available as a digital product. A competent person must confirm that its scope matches the work, assess the actual task, adapt the sequence and controls, coordinate it with the project arrangements and brief everyone involved.

Buying or downloading a template does not make it approved, suitable for the project or ready to issue. It does not replace drawings, manufacturer instructions, fixing information, COSHH assessments, asbestos and service information, or Principal Contractor review.

When is project-specific RAMS support useful?

Support may be useful where a package covers several component types or plots, substantial on-site cutting is required, work is in an occupied building, access or handling is difficult, fire or acoustic details must be protected, or the Principal Contractor has returned generic RAMS for revision.

For projects in Watford, Hertfordshire, London and the South East, send the drawings and schedules, component and weight information, fixing details, cutting and extraction arrangements, access plan, COSHH information, programme and Principal Contractor requirements. IMERI H&S Partners can then confirm an appropriate scope for project-specific RAMS support.

Official sources

This guide provides general information, not project-specific RAMS, a COSHH assessment, an access plan or approval of an installation method. Contractors and project duty holders must assess the actual work and use current design, product and site information.