CDM 2015 · Information flow · Mobilisation

Principal Designer to Principal Contractor handover: what information is needed?

The shift into construction is not a one-off document drop. The Principal Contractor needs current, usable information to plan the construction phase, while the Principal Designer must remain connected to design and risk decisions for as long as the appointment continues.

Before construction starts, the Principal Designer should give the Principal Contractor the pre-construction information, design information and risk information it holds that are relevant to planning the construction phase and drawing up the Construction Phase Plan. The transfer should identify current documents, known limits, unresolved matters, owners and dates—not present assumptions as settled facts.

CDM 2015 does not prescribe a document called a “Principal Designer handover pack”. A controlled pack, register and meeting record are practical ways to demonstrate that the required information was provided and understood. They do not replace the continuing duty to liaise and share relevant information.

Not a single handover event

Design commonly continues after work starts through specialist design, temporary works, substitutions and site-led changes. The information route must therefore remain active throughout the Principal Designer's appointment.

What does CDM 2015 require?

Regulation 11 requires the Principal Designer to liaise with the Principal Contractor for the duration of the Principal Designer's appointment and share information relevant to planning, managing and monitoring the construction phase and coordinating health and safety. HSE describes the same relationship as keeping the Principal Contractor informed about risks that need to be controlled during construction.

Regulation 12 adds a specific Construction Phase Plan duty: the Principal Designer must provide the Principal Contractor with all information it holds that is relevant to the plan, including pre-construction information obtained from the client and relevant information received from designers.

The exchange is two-way. The Principal Contractor must liaise with the client and Principal Designer, and must provide the Principal Designer with information in its possession that is relevant to the Health and Safety File. A useful transition process therefore establishes both routes rather than treating the Principal Contractor as a passive recipient.

What should the pre-start handover contain?

The contents should be proportionate to the project and should point to controlled source information rather than duplicating an uncontrolled archive.

1. Duty holders, scope and current status

  • the client, Principal Designer, Principal Contractor, designers and known contractors;
  • the written appointments, project scope and boundaries relevant to each role;
  • the planned site-start date, programme assumptions and key construction stages; and
  • the agreed communication, meeting, reporting and escalation routes.

2. Current pre-construction information

Provide an indexed set of relevant surveys, existing records, site and structure information, utility information, asbestos information, access and neighbouring constraints, client arrangements and other facts needed for planning. State the revision, date, source, coverage and known limitation of each item. Do not label an old survey or unverified drawing “for construction” merely because no newer record is available.

3. Significant design risks and decisions

Explain the significant and unusual risks that could not be eliminated, the decisions already taken to reduce them and the information needed to control what remains. Link each item to the relevant drawing, specification, model, calculation or design-risk record. Avoid sending a generic hazard list that hides the issues requiring action.

4. Design status, responsibilities and change control

  • current design deliverables and their suitability or issue status;
  • outstanding design, surveys, approvals, selections and technical queries;
  • design responsibility for specialist packages and temporary works;
  • review, coordination and acceptance routes for contractor proposals; and
  • how changes, substitutions and site discoveries will be assessed and communicated.

5. Construction Phase Plan inputs

Identify the information that should shape site establishment, logistics, sequencing, welfare, public protection, emergency arrangements, significant-risk controls and coordination between contractors. The Principal Contractor owns preparation and implementation of the plan on a multi-contractor project; the Principal Designer supports that work by providing relevant information, not by silently assuming the Principal Contractor's construction-phase duties.

6. Health and Safety File arrangements

Agree the file structure, information requirements, contributors, formats, review points and handover timetable early. The file should develop from relevant design and construction information, not be assembled from every project document at completion. See the separate guide to Health and Safety File contents and handover.

How should the handover meeting be run?

Issue the indexed information early enough for the Principal Contractor to review it before the meeting. The discussion should test whether the information is usable for planning—not simply record that files were sent.

  1. Confirm the duty-holder appointments, scope and authority of the people attending.
  2. Walk through the current design and pre-construction information registers.
  3. Identify significant risks, interfaces and decisions affecting mobilisation or sequence.
  4. Test how each issue will be addressed in the Construction Phase Plan, logistics, RAMS, design or a separate control.
  5. Record missing or uncertain information as actions with an owner, due date and affected hold point.
  6. Agree the continuing design-review, change-control and information-distribution process.
  7. Confirm the Health and Safety File contribution and review arrangements.

The wider contractor pre-start meeting checklist can be used to coordinate RAMS, permits, welfare, logistics, emergencies and mobilisation evidence around this duty-holder handover.

How should missing information and open items be controlled?

A project does not need every final drawing before any work can begin, but the information must be sufficient for the work about to start. Record each gap against the decision or activity that depends on it.

RecordWhat it should showControl
Information gapThe missing survey, design, decision or confirmation and why it matters.Named owner and realistic due date.
AssumptionThe basis, source, limit and what must verify it.Do not present it as confirmed fact.
Hold pointThe work or release that cannot proceed safely without the information.Authorised close-out before release.
Interim controlA temporary restriction or sequence that manages risk while information develops.Defined expiry or review trigger.

Safety-critical gaps should not be hidden in meeting minutes. Place them in the live action, design or risk register used by the people controlling the affected work, and connect them to the Construction Phase Plan or other relevant control.

What information must keep flowing after site start?

Construction starting does not end the pre-construction phase for design work that is still being prepared or changed. The Principal Designer and Principal Contractor should continue to exchange information about:

  • design changes, substitutions, technical queries and specialist proposals;
  • new surveys, site discoveries and conflicts with existing information;
  • temporary works or construction methods that affect permanent design risk;
  • programme or sequence changes that create different simultaneous or successive work;
  • incidents, near misses or monitoring findings that expose a design or coordination issue;
  • updated risks and information needed for the Construction Phase Plan; and
  • as-built and residual information needed for the Health and Safety File.

Where a change affects the construction arrangements, the Principal Contractor should decide whether the plan, site rules, logistics, permits or contractor controls need revision. The separate guide explains when the Construction Phase Plan should be updated.

What if the Principal Designer appointment ends before the project?

The role should continue for as long as Principal Designer functions need to be performed. If the appointment concludes before the project ends, Regulation 12 requires the Principal Designer to pass the Health and Safety File to the Principal Contractor. HSE guidance also expects a full briefing on relevant design and health and safety matters so the Principal Contractor can manage the remaining construction-phase responsibilities.

Record the appointment end date, the design status, outstanding risks and actions, the file revision transferred, future contributors and who now controls each live register. Ending an appointment should not create an unowned design or information gap.

A buyer checklist before construction starts

  1. Confirm the written Principal Designer and Principal Contractor appointments and their scope.
  2. Give the Principal Contractor enough time to review the information before mobilisation.
  3. Issue a controlled index showing revisions, status, source and known limitations.
  4. Connect significant design risks to drawings, decisions, owners and construction controls.
  5. Record information gaps, assumptions, actions and safety-critical hold points.
  6. Confirm that the Construction Phase Plan uses the relevant information before site setup.
  7. Agree continuing liaison, design-change and Health and Safety File processes.
  8. Revisit the arrangements when appointments, design control, scope or programme changes.

Official sources

This guide was checked against current official information on 18 November 2026:

This is general Great Britain construction guidance. The necessary information, timing and review depth depend on the project, appointments, design status and risks. A handover record does not transfer or replace any duty holder's legal responsibilities.