Construction Phase Plans · Change control

When should a Construction Phase Plan be updated?

The Construction Phase Plan is not finished when the site opens. It must remain a usable account of the arrangements, rules and measures controlling the current construction phase—not a snapshot of the tender or mobilisation meeting.

Review the Construction Phase Plan regularly and whenever new information, a project change or site evidence could affect the arrangements for managing health and safety. Update the affected content promptly, coordinate the consequences with relevant duty holders and contractors, and communicate the current controls to the people who must follow them.

There is no universal monthly-update rule

CDM 2015 requires the plan to be appropriately reviewed, updated and revised from time to time throughout the project so that it remains sufficient. A calendar review can support that duty, but it does not replace an event-driven review when a material change occurs.

Who is responsible for updating the Construction Phase Plan?

On a project involving more than one contractor, the Principal Contractor must ensure that the plan is reviewed, updated and revised throughout the project. On a single-contractor project, the contractor prepares the plan and must keep it fit for the live work.

The client must ensure that a plan is drawn up before construction starts and that the Principal Contractor or contractor receives the relevant information needed. The Principal Designer assists by passing relevant pre-construction information and design information to the Principal Contractor. Designers and contractors must continue to cooperate and provide information when their work or design changes.

A consultant can draft or review the document, but that does not transfer the Principal Contractor's or contractor's control of the construction phase. The person issuing a revision needs reliable information from the people managing design, temporary works, logistics, work packages and the site.

How often should the plan be reviewed?

Use two connected review routes:

  • Planned review: a proportionate recurring check linked to project meetings, phase changes or the management review cycle; and
  • Change-triggered review: an immediate or prompt check when information or conditions change, an incident occurs or monitoring shows that the arrangements may no longer be effective.

The planned interval should reflect the project's complexity, pace, risk profile and rate of change. A rapidly changing groundworks or structural phase may need more frequent attention than a stable finishing phase. Recording “reviewed—no change required” can be useful when it reflects a genuine check, but repeatedly changing only the date is not evidence that the plan remains sufficient.

Construction Phase Plan update triggers

Design, scope and information changes

Review the plan when drawings, specifications, residual design risks, surveys, service information, asbestos information, temporary-works requirements or the project scope changes. Confirm whether the change affects sequence, competence, access, exclusion, permits, emergency arrangements or another contractor.

Programme, phase and contractor changes

A new work package, contractor, specialist, shift pattern, acceleration, resequencing or occupation phase can create different interfaces and supervision needs. Review the plan before the changed arrangement becomes normal site practice.

Site layout, logistics and public interfaces

Update affected arrangements when hoarding, gates, pedestrian routes, traffic routes, delivery areas, unloading, lifting zones, storage, welfare, fire points, security or public protection changes. A logistics drawing can sit outside the main document, but the CPP should identify the current system and control process.

New or changed significant risks

Review the plan when the work introduces or materially changes excavation, structural stability, work at height, lifting, demolition, confined spaces, live services, hazardous substances or other Schedule 3 risks. Link the project-wide arrangements to the relevant design, permit, temporary-works or RAMS controls without copying every task method into the CPP.

Monitoring, incidents and enforcement concerns

An incident, significant near miss, failed inspection, worker concern, repeated non-compliance or regulatory visit may show that the written arrangement is incomplete or not working. Control the immediate risk first, then revise the plan and related documents where the finding affects the management system.

Welfare, emergencies and workforce needs

Review welfare and emergency sections when workforce numbers, shifts, work locations, hazardous work, first-aid cover, fire arrangements, rescue needs or communication requirements change. Suitable welfare must be available from the start and maintained throughout the construction phase.

A practical CPP update process

  1. Define the trigger. Record what changed, when it takes effect and which people, work areas or phases may be affected.
  2. Gather current information. Obtain the approved design, programme, site information, contractor proposals, inspections and specialist input needed to assess the change.
  3. Control immediate risk. Do not wait for a document revision before stopping or restricting unsafe work. Use a hold point or temporary control where necessary.
  4. Coordinate the impact. Involve the client, Principal Designer, designers, contractors and specialists whose duties, information or work interfaces are affected.
  5. Revise the relevant arrangements. Update the specific CPP sections, site rules, referenced drawings, registers or appendices that need to change. Remove superseded information.
  6. Check connected documents. Confirm whether RAMS, COSHH assessments, permits, temporary-works records, logistics plans, fire arrangements, inductions or the Health and Safety File also need revision.
  7. Issue and communicate. Give the revision a clear status, record who checked it and brief the affected managers, supervisors and workers before the new arrangement is relied upon.
  8. Verify implementation. Inspect the site and monitor the work to confirm that the revised arrangement exists in practice and remains effective.

Use the contractor pre-start meeting checklist when a new package or mobilisation creates several connected actions. For the plan's overall content and responsibilities, see what goes in a Construction Phase Plan.

What revision evidence should be kept?

A proportionate change record should make the current plan and decision trail easy to understand. Record:

  • the revision number, issue date, status and document owner;
  • the change trigger and information reviewed;
  • the sections, site rules, drawings or appendices changed;
  • the person who prepared and checked the revision;
  • actions, owners, due dates and any pre-start or pre-task hold points;
  • who received or was briefed on the change; and
  • how superseded copies were withdrawn from points of use.

Keep the record proportionate. A short revision note can be enough for a focused change; a major phase or design change may need a formal coordinated review. Do not create a long log that hides whether the current site arrangement is actually controlled.

How should CPP changes be communicated?

Send the affected information to the people who manage or carry out the work, not only to a document portal. Depending on the change, communication may include a management meeting, revised induction or site rule, supervisor briefing, toolbox talk, RAMS re-brief, updated drawing at the workface or a permit and hold-point release.

Check understanding where the change is safety-critical, complex or affects language and literacy needs. Then inspect the physical arrangement and observe the work. A revision marked “issued” is not effective if the gate route, exclusion zone, rescue plan or work sequence still follows the superseded version.

Official sources

This guide was checked against current official information on 17 November 2026:

This is general UK construction guidance. Review frequency, records and communication should reflect the project, duty-holder arrangements, information and risks. Updating the CPP does not replace the assessments, designs, permits, inspections or specialist controls required for the work.