Construction planning · Contractor mobilisation

Construction contractor pre-start meeting checklist.

A useful pre-start meeting turns the contract scope, design information, Construction Phase Plan and contractor's working method into clear decisions before people, plant and materials arrive. This checklist focuses on the issues that should be resolved—not on creating another ceremonial signature sheet.

Hold the contractor pre-start meeting early enough to change the plan, but late enough for the scope, team and working method to be identifiable. Confirm the role and work package, exchange missing information, test the proposed sequence and interfaces, agree the documents and physical controls needed before mobilisation, and record who must close each action.

Is a “pre-start meeting” a named legal requirement?

CDM 2015 does not prescribe a meeting with that title. It is a practical way to support duties to plan, manage, monitor, cooperate, coordinate, provide information and ensure suitable arrangements are in place. Holding a meeting does not, by itself, prove those duties have been met.

When should the contractor pre-start meeting happen?

For a work package, hold it before the contractor mobilises and before any activity that depends on unresolved design, temporary works, permits, isolations, access or lifting arrangements. A principal contractor should be appointed early enough to plan the construction phase and liaise with the client and Principal Designer. The Construction Phase Plan must be prepared before the construction phase begins and kept under review.

Do not wait until operatives are standing at the gate. HSE advises discussing proposed methods, expected equipment and facilities, risks to other people and agreed controls before contracts are let. Where procurement timing makes that impossible, record the remaining conditions and prevent mobilisation or the affected activity until they are closed.

A project-wide mobilisation meeting does not replace package-specific reviews. Groundworks, structural steel, façade, lifting, temporary works and commissioning packages can require different people, information and hold points.

Who should attend?

Invite the people who can answer the technical questions and make or accept actions. Depending on the project and package, this may include:

  • the client or project manager where a client decision, access arrangement or retained-site interface is involved;
  • the Principal Contractor's project or site manager and relevant health and safety support;
  • the contractor's contract manager, proposed supervisor and person responsible for the RAMS;
  • the Principal Designer or relevant designer where design information, residual risk or change is involved;
  • the Temporary Works Coordinator, lifting team, logistics manager or other specialist for risk-dependent matters; and
  • the person controlling occupied premises, isolations, permits or adjacent operations where applicable.

A commercial attendee can confirm scope and programme but may not be able to explain the method, competence or design assumptions. Do not mark a technical point “agreed” when the person able to resolve it was absent.

What information should be available before the meeting?

Issue the relevant information in time for attendees to review it. The pack should be proportionate to the package, but commonly includes:

  • the order, scope, drawings, specification, programme and responsibility boundaries;
  • relevant pre-construction information, surveys, existing Health and Safety File information and significant residual design risks;
  • the current Construction Phase Plan, site rules, logistics plan and emergency arrangements;
  • the contractor's proposed sequence, RAMS, COSHH information and inspection or test requirements;
  • details of the proposed manager, supervisor, workforce, subcontractors and specialist competence;
  • plant, access equipment, lifting, delivery, storage and waste arrangements; and
  • temporary-works, design, permit, isolation and handover information relevant to the package.

Unfinished information can be reviewed if it is clearly identified as a draft and the consequences are controlled. Do not allow a draft drawing, unapproved temporary-work design or generic RAMS to become accepted simply because it appeared in the meeting pack.

Construction contractor pre-start meeting agenda

1. Confirm the scope and boundaries

Define what the contractor will and will not do, the work areas, interfaces with other packages, design responsibility, attendance requirements, exclusions and completion or handover criteria. Resolve contradictions between the quotation, order, drawings and programme.

2. Confirm duty holders, management and communication

Record the client, Principal Designer, Principal Contractor and relevant designers and contractors. Name the package manager and supervisor, confirm escalation routes, working hours, reporting lines and who can stop or release work.

3. Review information gaps and design status

List missing surveys, approvals, calculations, specifications, service information and design decisions. Identify who will provide each item and by when. Where design continues during construction, agree how changes and residual risks will be communicated to the Principal Designer and Principal Contractor.

4. Test the work sequence and interfaces

Walk through delivery, set-up, access, work sequence, inspection, protection and handover. Check simultaneous and successive work, public or occupied-area interfaces, exclusion zones, shared access, scaffold or temporary-work reliance and the effect on other contractors.

5. Review RAMS and briefing arrangements

Confirm that the RAMS match the actual scope, people, plant, products, location and Principal Contractor arrangements. Record comments and revision responsibility. Agree who will brief the workforce, how understanding and acceptance will be recorded, and when the method must be reviewed. A template requires project-specific assessment, adaptation and briefing; it is not automatically approved or site-ready.

6. Agree temporary works, lifting and permits

Identify temporary works and the relevant design, checking, coordination, erection, inspection and loading controls. Confirm lifting responsibilities and documentation where lifting is involved. Define permits, isolations, service releases, hot-work controls and any other formal authorisation needed before the task or stage starts.

7. Plan logistics and protection of others

Agree delivery booking, vehicle routes, unloading, traffic marshals, pedestrian segregation, storage, waste, security and housekeeping. Consider neighbours, the public, roads, railways, schools, occupied premises and environmental constraints where they are affected.

8. Confirm welfare and emergency arrangements

Verify that suitable welfare will be available from the start and maintained for the workforce. Review first aid, fire, spill, rescue and evacuation arrangements against the package risks. Name trained people and check that rescue equipment or external assistance can be accessed in time.

9. Confirm competence, induction and supervision

Check the proposed organisation and risk-relevant competence rather than collecting unrelated cards. Agree site induction, task briefing, toolbox talk and supervision arrangements, including language, literacy, young-worker or new-starter needs.

10. Decide whether work is ready to start

Separate actions that can remain open during mobilisation from hold points that prevent mobilisation, energisation, loading, entry or the affected work. The final decision should be clear: ready, ready subject to named conditions, or not ready.

What should the meeting produce?

A useful record is short enough to use and specific enough to control the work. It should include:

  • attendees, roles, date, package and documents reviewed with revision references;
  • decisions, assumptions and information still required;
  • an action owner and due date for every open item;
  • clearly marked pre-mobilisation and pre-task hold points;
  • the status of RAMS, design, permits, logistics, welfare and emergency arrangements; and
  • the person authorised to confirm that each hold point is closed.

Circulate the record promptly and transfer relevant decisions into the Construction Phase Plan, RAMS, logistics information, temporary-works register or other controlled document. Minutes are not a parallel management system.

If an action is safety-critical, evidence its closure. “Contractor to confirm” is not a close-out record.

When should the pre-start review be repeated?

Repeat or formally revisit the review when the decision basis changes materially. Triggers can include:

  • a revised design, scope, sequence, programme or work area;
  • a new contractor, supervisor, specialist, plant item or product;
  • unexpected services, structure, contamination, ground or occupied-area conditions;
  • a significant incident, failed inspection, enforcement concern or repeated non-compliance;
  • a change to access, temporary works, lifting, traffic, isolations or emergency arrangements; or
  • the work pausing long enough for the original arrangements or team knowledge to become unreliable.

The review can be a focused change meeting rather than a complete restart. Update the affected documents, brief the people exposed to the change and retain an auditable decision.

Official sources

This guide was checked against current official information on 15 November 2026:

This checklist is general UK construction guidance. The meeting scope and evidence should reflect the project, appointment, package and risks. A meeting record does not replace competent planning, design, assessment, supervision or statutory inspections.