RAMS · MEWPs · Work at height

MEWP operation RAMS: what contractors should include.

A mobile elevating work platform can provide controlled access, but only when the machine suits the task and site. This guide explains what contractors should confirm before a boom lift or scissor lift is delivered, moved or raised for routine construction access.

MEWP RAMS should identify the specific machine and task, operator competence and familiarisation, route and set-up position, ground and overhead conditions, people and traffic interfaces, pre-use and examination evidence, operating limits, falling-object controls, and a practised emergency-lowering and rescue plan.

HSE says the hazards should be identified in a risk assessment and suitable controls put in place. A generic instruction to use a trained operator, wear a harness and follow the manufacturer's guidance does not show that the selected MEWP can safely reach the work from the available ground without overload, overturning, collision, entrapment or exposing people below.

The method should align with the Construction Phase Plan, traffic and lifting arrangements, overhead-service information, exclusion zones, permit systems, weather limits and Principal Contractor rules.

Select the right MEWP for the task and site

Define what will be done from the platform, where it must reach and how long the work will take. Confirm the required working height and outreach, platform dimensions, safe working load, number of people, tools and materials, and whether the machine will travel or work elevated.

Selection should also account for indoor or outdoor use, floor or ground capacity, slopes and level tolerance, rough terrain, tyres, outriggers, spreader plates, turning circle, tail or boom swing, access width and height, emissions, lighting, noise, wind rating and the position of overhead structures and services.

Do not select from height alone. A scissor lift, vertical mast, articulated boom and telescopic boom have different movement envelopes, stability needs and entrapment risks. Obtain competent advice from the supplier or manufacturer when the task, site or machine limits are unclear.

What information should be available before work starts?

Confirm, where relevant:

  • the work location, drawings, required reach, task sequence, duration and materials or tools taken into the platform;
  • the chosen MEWP make, model, category, working envelope, safe working load, platform capacity and manufacturer's operating limits;
  • operator training for the relevant MEWP category, medical fitness where relevant and familiarisation with the specific make and model;
  • delivery dimensions, unloading method, access route, turning and manoeuvring space, slopes, edges, gates and overhead clearance;
  • ground or floor capacity, voids, cellars, trenches, manholes, temporary covers, uncompacted backfill and any engineered set-up requirements;
  • overhead steelwork, ceilings, services, live power lines, projections and other trapping or collision hazards throughout the movement envelope;
  • pedestrians, site traffic, public interfaces, adjacent work, falling-object risk and the required exclusion area;
  • weather forecast, wind limits, visibility, lighting and arrangements for suspending or securing the machine;
  • current inspection, maintenance and thorough-examination evidence, pre-use checks and a defect-reporting process;
  • the manufacturer's requirements for work restraint or fall arrest, the assessed anchorage and rescue implications; and
  • the named ground-rescue person, communication method, ground-control access, emergency-lowering steps and recovery arrangements.

Do not invent ground capacity, point loads, wind limits, outreach, safe working load, clearance from power lines or harness requirements. Use the machine manual, project information, supplier data and competent engineering or electrical advice where required.

Write the method in the order the work will happen

A project-specific sequence may cover:

  1. confirming the work area, selected machine, delivery route, ground or floor capacity, overhead hazards and interfaces;
  2. checking operator competence, model familiarisation, emergency roles, manufacturer information and inspection or examination records;
  3. receiving and unloading the MEWP in the controlled area under the agreed traffic arrangements;
  4. walking the travel and working route, establishing barriers and checking slopes, edges, voids, covers, services and changing conditions;
  5. completing and recording the appropriate pre-use and function checks, including ground controls and emergency lowering;
  6. positioning and levelling the machine, deploying outriggers and spreader plates where specified, and confirming clearances;
  7. loading only the planned people, tools and materials within the platform limits and securing loose items;
  8. raising and moving under controlled communication while monitoring the full movement envelope, people below and weather;
  9. lowering to the agreed safe position before relocation, charging, refuelling or leaving the machine unattended; and
  10. parking, isolating and securing the MEWP, reporting defects and closing the work area when the task ends.

Critical controls to address in MEWP RAMS

Ground conditions and stability

HSE advises using the platform on firm, level ground and checking that temporary covers can withstand the applied pressure. Trenches, manholes, voids, edges and uncompacted backfill can cause overturning. Confirm the route as well as the final set-up position, because ground risk can change while the machine travels.

Use outriggers, chocks and spreader plates as required by the machine manual and ground assessment. Do not use packing, bridge covers or improvised supports without competent confirmation. Stop for settlement, movement, alarm activation, unexpected slope, damaged surface or loss of level.

Entrapment, crushing and overhead obstructions

Map the operator's position and the complete boom or platform movement against steelwork, ceilings, services, scaffold, doorways and projections. Slow, deliberate movement and a suitable spotter may be required where visibility or clearance is restricted.

HSE warns that a control cover or shroud should not be relied on as general protection against entrapment. Where secondary guarding is selected, it must suit the specific application and its limitations must be understood. The primary controls remain suitable machine selection, route planning, operator awareness, supervision and a rescue plan.

People, traffic and falling objects

Separate the MEWP from pedestrians, vehicles and adjacent work. Define who controls barriers and who may enter the area. Prevent any part of the platform or boom from extending into an uncontrolled traffic route, public area or another contractor's work zone.

Keep the platform tidy, secure suitable tools and materials, and establish a proportionate exclusion area below. Toe boards and tool restraints support the arrangements but do not make it acceptable to work over unprotected people.

Falls, guardrails and restraint

Keep platform gates closed and guardrails complete. Do not climb or stand on rails, use steps inside the basket, lean outside the platform or improvise extra height. Transfer from the platform at height should not be treated as routine use and needs specific competent planning and manufacturer confirmation.

Harness and lanyard arrangements depend on the machine type, manufacturer instructions and risk assessment. Where work restraint is required, use the designated manufacturer-provided anchorage and a compatible short restraint system that prevents the person reaching a fall position. Do not assume the same arrangement applies to every boom lift and scissor lift.

Power lines and services

Identify overhead electrical lines and other dangerous services before selecting the route or set-up position. HSE advises not operating a MEWP close to overhead cables. Required clearances and isolation arrangements must come from the relevant network operator, project information and competent electrical planning—not a guessed distance in generic RAMS.

Weather and visibility

Set the maximum operating wind speed from the machine rating and manufacturer information, considering gusts and the effect of panels, sheets or other materials. Stop for excessive wind, lightning, poor visibility, ice, snow or conditions that affect stability or control. Inspect the MEWP after severe weather before returning it to use.

Checks, defects and examination

Establish daily visual and functional checks, planned inspections and servicing in line with the manufacturer and risk assessment. Safety-critical defects require the MEWP to be taken out of service, isolated and reported; a tag or checklist must not be used to excuse an unresolved fault.

HSE states that MEWPs used to lift people must be thoroughly examined at least every six months, unless a competent-person examination scheme specifies otherwise. Check the current report and any defects or limitations rather than relying only on a sticker or hire note.

What should the emergency rescue plan cover?

HSE says there should be a plan for rescuing someone from a MEWP and that it should be practised. Someone on the ground should know what to do and how to operate the machine's ground controls. The plan should identify the named role, communication method, ground-control key or access, emergency lowering procedure, isolation and escalation arrangements.

Consider foreseeable scenarios: operator illness, control failure, platform entrapment, loss of power, machine immobilisation, a fallen or suspended person, blocked ground controls and the need to protect rescuers from traffic, electricity or crushing. Calling the fire and rescue service can be part of escalation, but it should not replace the immediate site arrangements needed for the selected machine and task.

Brief and practise the plan in a controlled way before relying on it. Confirm that rescue access remains available as the work area, barriers and adjacent activities change.

When routine MEWP RAMS are not enough

Stop and obtain the correct competent planning for work near live overhead conductors, use on a public highway, complex suspended or underslung work, leaving the platform at height, work over water, unusual ground or structural loading, lifting loads outside the platform's intended use, or any task beyond the manufacturer's limits.

Routine access RAMS should not be extended to cranes, telehandlers with personnel platforms, mast-climbing work platforms, façade-access systems or rope access. A change of machine, location, ground, task, weather, load, operator interface or nearby activity can require reassessment and rebriefing before the MEWP is used again.

Can a MEWP RAMS template be used?

A template can provide headings and a controlled starting structure for routine construction access. It cannot select the machine, prove the ground or floor, identify the movement envelope, verify the operator, set the weather limits or create a workable rescue plan for the actual site.

The MEWP Operation – Routine Construction Access RAMS template is available in the IMERI H&S Partners RAMS shop. Its scope should be checked before purchase and use. A competent person must assess and adapt it to the project, coordinate it with the manufacturer's information and site arrangements, and brief the workforce. Buying or completing a template does not make it automatically approved, suitable or site-ready.

Coordinate delivery and unloading with the material-delivery RAMS guidance, and ensure the MEWP arrangements are reflected in the relevant Construction Phase Plan and task RAMS.

When project-specific support is useful

Support is useful where the MEWP works near structures or services, ground or floor capacity needs confirmation, the route crosses traffic or occupied areas, materials are handled from the platform, several contractors share the area, or the Principal Contractor has returned generic RAMS for revision.

For projects in Watford, Hertfordshire, London and the South East, send the work location and task, required height and outreach, proposed MEWP details, operator information, route and set-up plan, ground or floor information, overhead hazards, weather limits, rescue arrangements and Principal Contractor requirements. IMERI H&S Partners can then confirm an appropriate scope for project-specific RAMS support.

Official sources

This guide was checked on 23 October 2026 against current HSE and legislation.gov.uk information:

Need project-specific MEWP RAMS?

Start with the task, machine and set-up area.

Send the required height and outreach, proposed MEWP, route, ground information, overhead hazards, operator details, weather limits, rescue plan and Principal Contractor requirements for a proportionate quotation.