RAMS · Tower scaffolds · Work at height

Mobile tower scaffold RAMS: what contractors should include.

A mobile access tower can provide collective fall protection, but only when the correct tower is assembled, inspected and used on a suitable site. This guide explains what contractors should establish before routine tower assembly, use, movement and dismantling.

Mobile tower scaffold RAMS should identify the task and tower configuration, manufacturer's instructions, competent people, safe assembly and dismantling method, ground and overhead conditions, stabilisers, platforms and guardrails, access, loading, exclusion and security arrangements, inspection regime, rules for use and movement, and the triggers for stopping and reassessing the work.

HSE says a tower must be suitable for the work and erected and dismantled by trained, competent people. Those using it also need training in the dangers and precautions. A generic statement to assemble the tower correctly and wear PPE does not establish that all compatible components are present, the ground will support the configuration, the platform is at the permitted height, or the team can move the tower safely.

First apply the work-at-height hierarchy: avoid the work at height where reasonably practicable, then prefer collective fall prevention. A tower may be a suitable option, but it should be selected against alternatives such as a fixed working platform, scaffold or MEWP for the actual task and location.

Select the tower for the task and location

Define the task, working height, platform size, duration, number of people, tools and materials, required reach and how often the work position will change. Confirm whether the tower is intended for indoor or outdoor use and whether doors, floor openings, ramps, kerbs, excavations, live traffic, occupied areas, overhead services or weather affect the planned position.

Identify the tower system, manufacturer and permitted configuration. The instruction manual should state the assembly sequence, bracing, stabilisers or outriggers, platform positions, safe working loads and maximum permitted height. Do not mix components from different systems or invent a configuration because parts appear to fit.

A standard mobile tower should not be selected where the task requires people to lean or climb outside its guardrails, bridge a gap, support a ladder, carry an unsuitable load or work beyond the manufacturer's limits. Choose different access equipment or obtain a properly designed specialist solution.

What information should be available before work starts?

Confirm, where relevant:

  • the work area, task, required platform height, duration, people, tools and materials;
  • the tower make, system, component list, configuration, safe working load and current manufacturer's instructions;
  • who will assemble, alter, inspect, use, move and dismantle the tower, and the evidence supporting their competence;
  • whether Advance Guardrail or Through-the-Trap is the specified safe assembly and dismantling method;
  • the ground or floor condition, level, capacity and any slopes, voids, covers, trenches, edges or fragile finishes;
  • the required castors or base plates, bracing, stabilisers, outriggers and platform positions for the selected configuration;
  • access and delivery routes, component handling, storage and separation from vehicles, pedestrians and the public;
  • overhead electrical lines, ceilings, services, beams, openings and other obstructions;
  • weather and wind restrictions, including the arrangements for taking the tower out of use;
  • inspection frequency, competent inspector, record format, defect isolation and handover arrangements; and
  • emergency arrangements for foreseeable illness, injury, instability, damaged components or a blocked access route.

Do not copy a generic base-to-height ratio, wind speed, load, stabiliser arrangement or platform spacing into the RAMS. Use the instruction manual for the identified tower and obtain competent advice where the required configuration or site condition is not covered.

Write the method in the order the work will happen

A project-specific sequence may cover:

  1. checking that work at height is necessary and that a tower is suitable for the task and site;
  2. confirming the tower system, manual, component list, configuration, competent team and inspection arrangements;
  3. receiving, unloading and storing components without damage or uncontrolled manual handling;
  4. isolating the assembly area and checking the ground, floor, overhead hazards and nearby activity;
  5. sorting and inspecting compatible components and removing damaged, contaminated or incorrect parts;
  6. assembling in the manufacturer's sequence using Advance Guardrail or Through-the-Trap, with the required bracing, platforms and stabilisers;
  7. levelling and securing the tower, locking castors and completing a competent inspection before first use;
  8. briefing users on access, loading, guardrails, exclusion, weather, alteration and defect rules;
  9. using, inspecting and—only where permitted—moving the tower under the agreed controls; and
  10. closing the area, dismantling by the safe method, checking components and storing or returning them securely.

Critical controls to address in tower RAMS

Competence and manufacturer's instructions

Allocate clear responsibilities. HSE requires competence to build, inspect, use and dismantle a mobile access tower. A card or certificate can help demonstrate training, but the contractor should still confirm that the person has the skills, knowledge and experience for the particular system, configuration and work.

Keep the manufacturer's instructions available to the assembly team and supervisor. Do not rely on memory where the system, configuration or component set has changed.

Assembly and dismantling

Use the Advance Guardrail or Through-the-Trap method specified for the tower so that a person does not stand on an unguarded platform. HSE identifies purpose-built trapdoor platforms, correctly positioned guardrails, safe internal access, stabilisers and toe boards as essential safety features.

Create an exclusion area around the assembly and dismantling work. Control dropped components, manual handling and incomplete-tower access. Never climb an incomplete structure outside the protected sequence or leave an incomplete tower available for others to use.

Stability and complete components

Place the tower on firm, level ground with locked castors or properly supported base plates. HSE expressly warns against using bricks or building blocks to support the tower. Fit the correct stabilisers or outriggers and every brace, platform, guardrail and toe board required by the instructions.

Account for slopes, voids, covers, floor edges, excavations, soft ground and temporary finishes. Keep the tower within the manufacturer's permitted height and configuration. Stop for settlement, movement, missing parts, damaged castors, loss of level or changes to the supporting surface.

Safe access, loading and use

Use the built-in ladder or staircase and enter through the platform trapdoor. Keep trapdoors closed where required, guardrails complete and access free of obstructions. Do not climb the outside, stand on guardrails, use a ladder or trestle on the platform, or create extra height with improvised items.

Keep people, tools and materials within the tower's safe working load. Plan how materials will reach the platform without overreaching, destabilising the structure or exposing people below. Toe boards and barriers support the controls but do not make it acceptable to work above an uncontrolled area.

Moving the tower

Prefer dismantling and reassembly where the route or configuration makes movement unsafe. Where the instructions permit a tower to be moved, HSE advises reducing it to a maximum height of 4 metres, checking for overhead obstructions and firm level ground, and pushing or pulling manually from the base only.

Never move a tower with people or materials on it or in windy conditions. Recheck level, castors, stabilisers, components and the new location before use. A move can affect stability and should trigger the inspection arrangements required by the risk assessment and instructions.

Weather, interfaces and security

Set stop-work arrangements for strong winds and other conditions that could affect stability or safe access. Do not add sheeting, netting, signs or other wind-catching material unless the tower and configuration have been competently assessed for it.

Separate the tower from vehicles, doors, cranes, overhead lines and adjacent work. Prevent unauthorised use during breaks and out of hours. Depending on the setting, this may require site fencing, local barriers, controlled ladder access or partial dismantling—not merely a warning sign.

What should the inspection and record cover?

HSE says all towers must be inspected by a competent person after assembly and at suitable regular intervals. They also need inspection when something happens that may affect stability or safety. For construction work where a person could fall 2 metres or more from the working platform, HSE states that inspection is required after assembly and every 7 days.

The check should follow the tower instructions and verify the location and support, level, castors or base plates, stabilisers, braces, platforms, trapdoors, access, guardrails, toe boards, components, configuration and any sign of damage, movement or unauthorised alteration. Record the result and defects. Stop work and isolate the tower when it is not safe; a tag does not replace the competent inspection or correction of faults.

Also inspect after substantial alteration, movement where safety may have been affected, impact, adverse weather or another event that could cause deterioration. Keep the report for the required period and make it available to the people controlling the work.

When routine mobile tower RAMS are not enough

Obtain the correct competent design and planning for non-standard or tied towers, bridging or cantilever arrangements, sheeted or enclosed towers, towers supporting hoists, unusual platform loads, work close to live overhead conductors, use on a public highway or any configuration outside the manufacturer's instructions.

Routine mobile tower RAMS should not be extended to general access scaffolds, stair towers, system scaffolds, birdcages, loading bays, temporary roofs, suspended scaffolds or proprietary structures with different design and inspection requirements. Reassess before changing the tower system, height, platform, ground, location, load, weather exposure or nearby activity.

Can a mobile tower scaffold RAMS template be used?

A template can provide a controlled structure for routine mobile tower assembly and use. It cannot select the tower, verify the component set, prove the ground or floor, confirm competence, establish the permitted configuration or inspect the erected tower.

The Mobile Tower Scaffold – Assembly & Use RAMS template is available in the IMERI H&S Partners RAMS shop. Check its named scope before purchase and use. A competent person must assess and adapt it to the project, tower instructions, site conditions and Principal Contractor arrangements, then brief the workforce. Buying or completing a template does not make it automatically approved, suitable or site-ready.

Coordinate the access arrangements with the Construction Phase Plan and task RAMS, and use the RAMS preparation and review guide to keep ownership and change control clear.

When project-specific support is useful

Support is useful where the work takes place beside excavations, traffic, overhead services or occupied areas; the floor or ground needs confirmation; the tower will be moved repeatedly; materials are handled at platform level; several contractors share the area; or the Principal Contractor has returned generic RAMS for revision.

For projects in Watford, Hertfordshire, London and the South East, send the task and work area, required height, tower make and system, configuration and manual, ground or floor information, access and movement route, loads, duration, competent-person and inspection arrangements, and Principal Contractor requirements. IMERI H&S Partners can then confirm an appropriate scope for project-specific RAMS support.

Official sources

This guide was checked on 24 October 2026 against current HSE and legislation.gov.uk information: