A workable method should identify the approved waterproofing system, substrate-release criteria, products, preparation, access, weather limits, application sequence, interfaces, inspections and handover—not treat every “membrane” as the same activity.

Waterproofing RAMS should establish the exact system, approved details, accepted substrate, work area, access, products, tools, environmental limits and inspection hold points before installation starts. They should then explain how the area will be released, prepared, protected, primed, waterproofed, checked and handed over for the actual project.

“Install waterproofing membrane” is not a complete method. Liquid-applied coatings, bonded or self-adhesive sheets, loose-laid systems, hot-applied products and torch-on membranes can involve materially different substances, equipment, competence, fire precautions and quality controls.

Coordinate the method with the construction COSHH guide, the abrasive-preparation guide, the manual-handling guide and the project's Construction Phase Plan.

Define the waterproofing system and installation boundary

State the roof, podium, balcony, basement, wet area, deck, wall, joint, upstand, outlet, penetration and termination zones included. Name the specified system and components rather than using “liquid membrane” or “sheet membrane” as a substitute for the product schedule and approved details.

Identify who provides the waterproofing design, approved drawings, manufacturer instructions and substrate acceptance criteria. RAMS should explain how the contractor will install the selected system safely; they should not redesign falls, drainage, joints, outlets, upstands, interfaces or structural support.

Set the boundary with screeding, roofing, tiling, façade, drainage, temporary works, services and follow-on trades. Clarify who prepares the substrate, who releases it, who seals penetrations, who protects the completed membrane and which inspection or test permits covering-up.

What information should be obtained before waterproofing starts?

Confirm, where relevant:

  • the latest specification, drawings, details, product schedule, manufacturer instructions and approved substitutions;
  • the membrane type, primer, adhesive, reinforcement, tapes, sealants, protection layers and compatible accessories;
  • the areas, levels, falls, outlets, joints, upstands, edges, penetrations, terminations and interfaces included;
  • the substrate material, condition, moisture, curing, cleanliness, profile, temperature and release criteria specified for the system;
  • any existing waterproofing, coatings, contamination, suspect materials or asbestos information relevant to preparation;
  • current product labels, safety data, COSHH assessments, storage limits, mixing instructions, ventilation needs and spill arrangements;
  • the preparation equipment, extraction, mixing equipment, rollers, brushes, squeegees, welding or jointing tools and inspection requirements;
  • whether any flame, hot-air, hot-melt, grinding or other ignition-producing process is genuinely required and authorised;
  • safe access, edge protection, openings, fragile surfaces, material-loading limits, rescue arrangements and exclusion zones;
  • forecast and local weather, wind, rain, surface temperature, dew or condensation restrictions and temporary protection;
  • occupied areas, fire routes, ventilation intakes, other trades, deliveries and work above or below the membrane zone; and
  • inspection, sampling, coverage or thickness, joint, test, protection and handover records required by the project.

Use a controlled substrate-release and installation sequence

A project-specific sequence may cover:

  1. confirming the latest approved system, drawings, work area, programme, responsibilities and hold points;
  2. inspecting access, edges, openings, lighting, weather exposure, fire routes and other work before materials are taken to the area;
  3. checking that the substrate and interfaces meet the system's stated release criteria and recording defects or incomplete work;
  4. agreeing segregation, storage, ventilation, waste, spill, emergency and material-distribution arrangements;
  5. checking product identity, batch, shelf life, packaging, compatibility, equipment and environmental conditions before use;
  6. preparing the substrate with the specified method and controlling dust, noise, vibration, debris and damage to retained work;
  7. completing an agreed trial or first-off area where required before full installation proceeds;
  8. applying primer, reinforcement, membrane, sheets, joints, laps, corners, penetrations and terminations in the specified order;
  9. maintaining exclusion and environmental controls during curing, cooling, bonding or joint completion;
  10. recording inspections and defects before protection, drainage layers, finishes or other work conceal the membrane;
  11. installing the specified protection without puncturing, contaminating or overloading the completed system; and
  12. handing over the controlled area with records, restrictions, outstanding items and repair locations clearly identified.

Critical controls to address in waterproofing RAMS

Roof edges, openings and fragile surfaces

Where waterproofing is carried out at height, the method must connect to the project's safe access and collective fall-prevention arrangements. HSE identifies roof edges, openings and fragile surfaces as key roof-work risks. Do not assume that a flat roof, podium or finished deck is safe merely because the membrane area looks level.

Record the access route, edge protection, covers, barriers, loading areas, material-transfer method and rescue arrangements that apply. Stop if protection is incomplete, an opening is unsecured, a surface may be fragile, weather makes access unsafe or the work moves outside the released zone.

Substrate preparation and construction dust

Match preparation to the accepted substrate and specified system. Grinding or scabbling concrete can generate very high levels of silica-containing dust. HSE advises controlling this at source, including suitable on-tool extraction, with correctly selected RPE where the assessment shows it is required.

Do not introduce grinding, chasing, sanding, flame-drying or chemical cleaning simply to recover an unsuitable substrate without checking the specification, hazards and approval route. Isolate the preparation area, protect outlets and adjacent finishes, collect waste safely and reassess suspect or unidentified material.

Primers, adhesives, resins, solvents and COSHH

Use the exact approved products and assess how they are mixed, applied, cured and cleaned from tools. A safety data sheet supports the COSHH assessment but is not the assessment itself. Consider vapour, mist, skin and eye contact, sensitisation, flammability, spills, contaminated rags, waste, storage and the effect on other people.

HSE notes that solvent vapours can build up in enclosed or poorly ventilated areas and that some products may also contain isocyanates. Select substitution, application method, segregation, ventilation and any RPE from the actual product and task. Do not decant products into unlabelled containers or use solvents to clean skin.

Conditional hot work and fire precautions

Do not write torching, hot-melt work or flame-drying into generic waterproofing RAMS unless it is part of the approved system and has been specifically planned. HSE defines roofing hot work as processes generating flame, sparks or heat and recommends considering whether cold-applied alternatives can design out the risk.

Where hot work is authorised, the method needs the project's permit arrangements, competent operatives, suitable equipment, gas-cylinder controls, combustible-material removal, protection of voids and openings, extinguishers, emergency arrangements and the required fire watch. Occupied buildings, timber construction, concealed cavities and combustible insulation require particular coordination.

Manual handling, material storage and distribution

Membrane rolls, boards, liquid containers, gas cylinders and equipment may be heavy, bulky or difficult to grip. Plan delivery sizes, weights, lifting aids, roof or floor loading, routes, stairs, openings and storage close to the point of use. Prevent rolls from moving, keep containers upright where required and do not overload access platforms or completed surfaces.

HSE's construction guidance prioritises avoiding or reducing manual handling, using suitable aids and delivering materials close to where they will be used. Team lifting or technique training can support the method but does not replace reducing the load, route or handling frequency.

Weather, wet surfaces and drainage

Define the system's permitted weather and substrate conditions from current manufacturer information. Rain, standing water, frost, condensation, heat or wind may affect both safety and installation quality. Secure loose sheets, packaging and tools, and stop before material can be blown from an edge or rain compromises the work.

Maintain safe dry access and control wet, primed or tacky areas. HSE requires construction traffic routes to be kept safe from slip and trip hazards. Keep outlets and temporary drainage effective, segregate curing zones and prevent workers or other trades from walking through uncured or unprotected membrane.

Other trades, occupied areas and completed work

Coordinate ventilation intakes, ignition sources, escape routes, public areas, work below and activities that can puncture or contaminate the membrane. Agree who controls re-entry and covering-up. Protection boards or temporary coverings should be compatible with the system and installed without concealing unresolved defects.

What should inspection and handover cover?

Define who inspects the substrate and each installation stage, what acceptance criteria apply and what evidence is retained. Records may include area release, weather and substrate conditions, product and batch details, mixing, primer, specified coverage or thickness, reinforcement, joints, laps, penetrations, terminations, repairs, protection and photographs.

Where a test is specified, identify its method, timing, responsible person, prerequisites and response to failure. Do not cover the membrane merely because another trade is waiting. Record damage, incomplete details, contamination or conditions outside the system limits and agree the repair and reinspection route.

When should waterproofing RAMS be reviewed?

Review the method when the system, product, substrate, preparation, area, access, weather, ventilation, equipment, hot-work status, interface, programme, inspection or protection arrangement changes. Stop and reassess after finding an unsuitable substrate, suspect material, missing edge protection, unplanned opening, incompatible product, damaged container, unexpected vapour, leak, fire risk or failed inspection.

Brief the workforce on the released area, product restrictions, environmental limits, access, fire and spill response, hold points, protection and stop-work conditions. Principal Contractor acceptance does not make a generic method suitable or transfer the contractor's responsibility for controlling its installation work.

When routine waterproofing RAMS are not enough

This scope does not provide waterproofing design, drainage design, structural verification, temporary-works design, fall-protection design, asbestos work, confined-space entry, rope access, specialist sprayed systems, hot-melt or torch-on work unless expressly planned, or approval to change a specified system.

It also does not replace approved details, manufacturer instructions, substrate surveys and release, COSHH assessments, fire arrangements, access plans, permits, product training, inspection and test plans, warranties or specialist competence required by the system.

Can a waterproofing membrane RAMS template be used?

A relevant template can provide a useful structure, but it cannot know the specified system, substrate, products, details, work area, access, weather, fire precautions, interfaces or inspection standard for the project.

The Liquid / Sheet Waterproofing Membranes RAMS template is available in the IMERI H&S Partners RAMS shop. Check that its named scope matches the actual system. A competent person must assess and adapt it to the project, products, substrate, sequence, equipment, access, workforce, environmental limits and Principal Contractor requirements, then brief the workforce.

Buying or completing a template does not make it automatically approved, suitable or site-ready. It does not replace design information, product data, COSHH assessment, competent supervision, inspection or the contractor's responsibility for the installation.

When is project-specific RAMS support useful?

Support may be useful where the system contains several components, work is at height, the building remains occupied, preparation is intrusive, solvents or hot work are involved, weather protection is complex, several trades share the area or generic RAMS have been returned for revision.

For projects in Watford, Hertfordshire, London and the South East, send the waterproofing specification, approved details, area schedule, substrate information, product data, access and weather constraints, equipment, programme and Principal Contractor rules. IMERI H&S Partners can then confirm an appropriate scope for project-specific RAMS support.

Official sources

This guide was checked on 4 November 2026 against the following current official sources:

Need project-specific waterproofing RAMS?

Start with the specified system, substrate and work area.

Send the waterproofing specification, approved details, area schedule, substrate information, product data, access and weather constraints, equipment, programme and Principal Contractor requirements for a proportionate RAMS quotation.