Landscaping RAMS should establish the approved layout, released work area, ground and buried-service information, materials, plant, access, deliveries, sequence, products, weather limits and inspection points before work starts. They should explain how the team will receive and distribute plants and soil, prepare the ground, complete planting or turfing, protect the work and hand it over.
“Carry out landscaping” is not a safe sequence. Topsoil placement, hand planting, turfing, machine excavation, bulk-bag handling, watering and product application involve different hazards and may require different competence, plant and controls.
Coordinate the method with the groundworks RAMS guide, the materials-delivery guide, the manual-handling guide and the project's Construction Phase Plan.
Define the landscaping package and its boundaries
State the beds, verges, lawns, planters, tree pits, courtyards, podiums or other areas included. Identify whether the work covers topsoil receipt and spreading, soil improvement, hand or machine preparation, planting, turfing, mulching, staking, watering, establishment or routine maintenance.
Use the latest landscape drawings, schedules and specification. Clarify responsibility for levels, drainage, retaining features, irrigation, waterproofing protection, imported-soil approval and the release of each area. RAMS should explain how the contractor will deliver the approved work safely; they should not redesign levels, drainage, structural planters or retaining structures.
Set the boundary with groundworkers, paving teams, drainage contractors, irrigation installers, scaffold or access providers and follow-on maintenance. Identify who releases the ground, who confirms services, who accepts soil and plants, and who protects completed areas.
What information should be obtained before landscaping starts?
Confirm, where relevant:
- the latest drawings, planting plans, schedules, specification, approved substitutions and phased handover requirements;
- existing and proposed levels, falls, drainage, tree pits, planters, edges, slopes, retaining features and load-sensitive areas;
- current underground-service plans, locating results, trial-hole or permit-to-dig requirements and any overhead-service constraints;
- ground release, contamination, invasive plant, sharp-object, asbestos or other abnormal-ground information supplied for the area;
- topsoil type, test or acceptance information, quantities, delivery form, stockpile location, handling method and spreading depth;
- plant and turf sizes, root balls, containers, weights, delivery restraints, unloading method, storage and watering needs;
- excavators, dumpers, loaders, rotavators, compactors, power tools, hand tools, lifting accessories and authorised operators;
- vehicle routes, pedestrian segregation, unloading zones, public interfaces, access widths, ground bearing and edge conditions;
- fertilisers, conditioners, mulches, fuels, adhesives or other products, with current labels, safety data and task-specific COSHH controls;
- weather, lighting, water supply, mud control, welfare, washing, waste and emergency arrangements; and
- inspection, planting, staking, watering, protection, establishment and handover records required by the project.
Use a controlled release, delivery and installation sequence
A project-specific sequence may cover:
- confirming the released area, current landscape information, responsibilities, programme and inspection points;
- checking services, levels, ground condition, access, edges, slopes, public interfaces and environmental restrictions;
- establishing vehicle routes, unloading zones, plant exclusion areas, material storage, pedestrian routes and mud controls;
- checking plant, tools, attachments, lifting accessories, operator authorisations and daily inspections;
- receiving plants, turf, topsoil and other materials without uncontrolled unloading, carrying or stockpiling;
- confirming soil and plant identity, condition, quantities and acceptance before distribution;
- preparing the ground with the approved hand or mechanical method while protecting services, drainage, retained work and people;
- placing and grading topsoil, excavating planting holes, installing plants or turf and applying approved supports or products;
- watering, protecting and segregating the completed work while equipment and waste are removed;
- inspecting levels, plants, turf, supports, protection, cleanliness and defects before release; and
- handing over maintenance restrictions, watering requirements, outstanding work and project records.
Critical controls to address in landscaping RAMS
Buried services, ground and excavation
Do not assume that shallow hand digging or planting holes are clear of services. HSE describes a safe excavation system as planning the work, locating and identifying buried services and using safe excavation methods. Plans are only an indication; where services may be affected, use suitable locating, marking and safe-digging arrangements with competent people.
Define the permitted digging method, depth and area. Stop if information conflicts with site findings, a service is unmarked, the ground is contaminated or unstable, an unexpected void or object is found, or the work needs deeper excavation, support or redesign.
Mobile plant, vehicles and pedestrians
Mini-excavators, dumpers, loaders and delivery vehicles require suitable routes, ground, visibility, separation and competent operators. HSE requires construction sites to keep pedestrians and vehicles apart and identifies exclusion, clearance, visibility, competent marshalling and secure attachments as key excavator controls.
Show the operating and slewing zones, pedestrian routes, protected marshalling position, reversing controls, loading points and stop procedure. Do not allow workers to enter the operating zone to guide a bucket, trim by hand or collect materials while plant remains live.
Deliveries, topsoil, plants and manual handling
Plan vehicle booking, restraints, unloading, storage and distribution before the delivery arrives. HSE's planting guidance recommends organising delivery and site layout to reduce carrying, including mechanised unloading or teamwork where appropriate.
Assess root balls, pots, turf rolls, bags, kerb-like edging, stakes and equipment by weight, size, grip, stability, route and frequency—not a single assumed weight limit. Use smaller units, handling aids and delivery close to the workface where reasonably practicable. Technique training or team lifting does not replace reducing the task risk.
Tools, noise and vibration
Select maintained tools and attachments for the actual soil and task. Rotavators, compactors, breakers, augers, saws and other powered equipment may create entanglement, ejection, noise or vibration risks. Keep guards and safety devices in place, isolate equipment before clearing or adjustment and control access around powered operations.
Where vibrating tools or hand-guided machinery are used, assess exposure from current equipment information and expected trigger time. HSE notes that regular exposure can cause permanent ill health and prioritises eliminating or reducing exposure, suitable low-vibration equipment, maintenance and controlled use.
Products, soil and hygiene
Assess fertilisers, conditioners, fuels, cleaners, adhesives and other substances for the way they will actually be used. COSHH also covers hazardous substances generated by work and some naturally occurring biological agents. Provide suitable storage, spill control, washing, skin protection and contaminated-waste arrangements.
Pesticide, herbicide or biocide application should not be added casually to general landscaping RAMS. HSE says pesticide use should follow a thorough risk assessment and that storage, use and disposal are strictly controlled. If such products are genuinely required, confirm authorisation, competence, product approval, label conditions and a separate task-specific method.
Weather, terrain and the public
Rain, heat, frost, wind and poor light can change ground stability, access, visibility, lifting and product conditions. Control mud on paths and roads, keep temporary routes suitable, prevent stockpiles and equipment encroaching on escapes or public areas, and secure lightweight materials.
Identify slopes, open holes, water, edges, uneven ground and newly irrigated or turfed areas. Use barriers and signs where people could enter unfinished work, but do not rely on signs alone where physical segregation is needed.
What should inspection and handover cover?
Define who checks the released ground, soil, plants, levels, holes, supports, products, watering and completed areas. Records may include service clearance, delivery and material details, soil acceptance, plant condition, inspection photographs, defects, protection, watering and maintenance instructions.
Do not hand over or cover an area merely because the programme is pressing. Record damaged plants, poor ground, incorrect material, exposed services, failed drainage, unstable stakes, unsafe edges or incomplete protection and agree the corrective and reinspection route.
When should landscaping RAMS be reviewed?
Review the method when the drawing, area, levels, services, soil, plant sizes, delivery, plant, equipment, digging depth, product, weather, public interface, programme or inspection requirement changes. Stop and reassess after unexpected ground, contamination, an unrecorded service, unstable excavation, plant defect, spill, damaged waterproofing, near miss or instruction that changes the work.
Brief the workforce on the released area, traffic routes, service controls, plant exclusion zones, handling plan, products, hygiene, weather limits, inspection points and stop-work conditions. Principal Contractor acceptance does not make a generic method suitable or transfer the contractor's responsibility for the landscaping work.
When routine landscaping RAMS are not enough
This scope does not cover tree surgery, chainsaw work, climbing, pesticide application, deep or supported excavation, confined spaces, structural retaining work, crane lifting, lifting people, traffic control on a public highway or design of levels, drainage, planters or temporary works unless expressly planned with the required specialist input.
It also does not replace landscape drawings and specifications, service information and permits, soil or contamination reports, COSHH assessments, plant lift plans where required, product labels, operator competence, environmental controls, inspection plans or maintenance instructions.
Can a landscaping, planting and topsoil RAMS template be used?
A relevant template can provide a useful structure, but it cannot know the drawings, ground, services, levels, plants, soil, deliveries, plant, products, weather, public interface or inspection standard for the project.
The Landscaping, Planting & Topsoil Works RAMS template is available in the IMERI H&S Partners RAMS shop. Check that its named scope matches the actual work. A competent person must assess and adapt it to the project, ground, services, materials, sequence, plant, equipment, access, workforce, environmental conditions and Principal Contractor requirements, then brief the workforce.
Buying or completing a template does not make it automatically approved, suitable or site-ready. It does not replace drawings, service information, competent supervision, COSHH assessment, inspection or the contractor's responsibility for the work.
When is project-specific RAMS support useful?
Support may be useful where landscaping interfaces with occupied areas, buried services, vehicle routes, podiums, waterproofing, significant level changes, bulk deliveries, mobile plant, public access or several contractors, or where generic RAMS have been returned for revision.
For projects in Watford, Hertfordshire, London and the South East, send the landscape drawings and schedule, work areas, levels, service and ground information, materials, plant, access and delivery plan, products, programme and Principal Contractor requirements. IMERI H&S Partners can then confirm an appropriate scope for project-specific RAMS support.
Official sources
This guide was checked on 5 November 2026 against the following current official sources: