Soft-strip RAMS should define exactly what is to be removed and retained, confirm the asbestos and other pre-construction information, identify structural boundaries and service isolations, set the strip-out sequence, and control dust, falling materials, access, occupied areas, manual handling, tools, waste movements and unexpected findings.
Under CDM 2015, contractors must plan, manage and monitor the work under their control and coordinate it with others. Calling work “non-structural” is not a control by itself: the team needs reliable information and clear hold points so it does not disturb asbestos-containing materials, live services, load-bearing elements or stability-critical construction.
The method should align with the pre-construction information, the Construction Phase Plan and project arrangements, survey findings, drawings, waste plan, building-occupier controls and Principal Contractor requirements.
Define the work and its limits
State the building, floor, room or zone and list the specific finishes, fittings and non-load-bearing items to be removed. Examples may include identified floor coverings, sanitaryware, kitchen units, doors, suspended ceilings, lightweight partitions, redundant containment and loose fixtures where the survey and project information support that scope.
Mark retained walls, ceilings, floors, services, finishes, protection, escape routes and occupied areas. Identify items for reuse separately from waste, and state who confirms that a service or component is redundant before disconnection or removal.
Keep routine soft-strip RAMS within their assessed boundary. Structural demolition or alteration, removal of load-bearing or stability-critical elements, asbestos work, live-service work, hot work, confined spaces, complex lifting, work needing engineered temporary works and unidentified hazardous-material removal require separate competent planning.
What information should be available before work starts?
Confirm, where relevant:
- the latest strip-out drawings, room data, removal schedule, photographs and retained-item information;
- a refurbishment or demolition asbestos survey that covers the actual location and depth of the proposed disturbance;
- information about the form and condition of the structure, previous alterations and any elements that must not be disturbed;
- drawings, labels and survey information for electrical, gas, water, heating, ventilation, data, security and other services;
- the isolation, lock-off, proving-dead, draining or disconnection process and the competent people authorised to complete it;
- known lead coatings, mould, bird or rodent contamination, sharps, pressurised systems, stored energy and other hazardous substances or conditions;
- occupied areas, neighbours, public interfaces, access routes, escape arrangements, permitted hours, noise and dust restrictions;
- work-at-height access, openings, floor capacity, material-drop restrictions and authorised loading or storage zones;
- tools, on-tool extraction, screening, ventilation, cleaning method and any required respiratory protective equipment;
- waste classification, segregation, internal routes, containers, skips, collection arrangements and transfer responsibilities; and
- inspection hold points, permits, handover standards and the people authorised to approve changes.
A management survey alone may not be sufficient where intrusive refurbishment work will disturb concealed building fabric. The survey scope must match the work. If the relevant area has not been adequately surveyed, do not begin intrusive strip-out there.
Write the method in the order the work will happen
A project-specific sequence may cover:
- confirming the released area, current drawings, removal schedule, surveys, isolations and authority to start;
- walking the area with the responsible site person and marking retained items, restricted zones and stop-work boundaries;
- establishing secure access, screening, warning signs, protection, lighting, ventilation, emergency routes and waste routes;
- removing loose contents and salvage items without disturbing the building fabric outside the surveyed scope;
- having competent trades isolate, lock off, prove dead, drain or disconnect relevant services and record the status;
- removing identified finishes and fixtures in the planned order, using suitable access and controlled tools;
- maintaining stability and stopping before any element whose function, support, service status or material is uncertain;
- controlling dust at source, keeping the work zone segregated and cleaning without dry sweeping;
- moving waste in manageable loads through the agreed route and segregating it into the designated containers;
- inspecting exposed areas for unexpected materials, damage or service conflicts at defined hold points; and
- making the area safe, recording changes and handing it over before another trade or occupied-area boundary changes.
Critical controls to address in soft-strip RAMS
Asbestos and unexpected materials
Check that the asbestos information is suitable for the exact disturbance planned and brief the relevant findings before work starts. Drawings and labels should help the team identify surveyed areas, exclusions and known asbestos-containing materials; they do not remove the need to stop when conditions differ from the information.
Stop work, prevent access and report immediately if workers find suspect insulation, board, coating, debris or other material that was not identified, or if the survey does not cover the area being opened. Do not sample, break or clear suspect material under general soft-strip RAMS.
Structure, stability and retained construction
Non-structural work still needs structural boundaries. Identify load-bearing walls, bracing, floors, roof members, lintels, shafts, facade restraints and temporary works that must not be altered. The removal sequence must not create uncontrolled collapse, falling materials or excessive loading.
Stop if an item is unexpectedly heavy, tied into a retained element, carrying another component, concealing movement or damage, or not shown clearly on the information. Refer structural uncertainty to the responsible designer, engineer or project team before continuing.
Service isolation and stored energy
Understand the building services and liaise with the occupier and relevant trades. Where strip-out could disturb an electrical system, HSE advises isolating the relevant parts. Isolation must be secure so energy cannot be inadvertently reintroduced; labels or an assumption that a service is redundant are not enough.
Address electricity, gas, water, steam, compressed air, hydraulic or pneumatic pressure, batteries and mechanical movement as applicable. State who isolates, how the status is verified, what remains live and what happens if an unrecorded service is found.
Dust, hazardous substances and cleaning
HSE identifies soft-strip demolition as capable of producing high dust levels. Plan to reduce disturbance, restrict the number of people in the area, screen the work zone and use suitable extraction or suppression for the material and tool. Avoid dry sweeping; use an appropriate vacuum or damp-cleaning method.
The COSHH assessment should reflect the actual materials and process. Respiratory protection may still be required after other controls; where tight-fitting RPE is selected it must be suitable, face-fit tested and supported by the required clean-shaven seal, use and maintenance arrangements.
Falling materials, tools and access
Use a controlled removal direction and prevent people working beneath or beside unsecured materials. Support or restrain components before releasing fixings, and use suitable access equipment rather than standing on fixtures, improvised platforms or unstable debris.
Select tools for the known material and fixing. Guards, extraction and other safety devices must remain in place. Isolate equipment before clearing faults or changing accessories, and reassess the method where cutting or percussive tools could disturb hidden services, hazardous materials or retained construction.
Manual handling, sharp edges and waste routes
Plan how awkward panels, doors, sanitaryware, glazing, metal sections and bagged waste will be released, handled and moved. Break work into controlled sections only where doing so is safe, use mechanical aids, keep routes clear and avoid universal weight assumptions.
Control nails, screws, broken edges, sharp metal and glass at source. Segregate waste promptly into suitable containers without overfilling them. Coordinate internal movements, skips and collection vehicles so workers, occupants and the public are separated from the route.
Occupied buildings and neighbouring work
Where part of the premises remains occupied, define the physical boundary, working hours, access controls, noise and dust arrangements, shared services and communication route with the occupier. Protect escape routes and do not block or alter them without the project's authorised arrangements.
Coordinate temporary changes to ceilings, doors, compartment lines, alarms, security and environmental controls with the responsible project team. The strip-out method must not leave an occupied or handed-over area in an uncontrolled condition.
Brief the workforce and review the RAMS
Brief the actual area, removal and retention marks, survey findings, live-service boundaries, sequence, dust controls, waste route, occupied-area interface, hold points and stop-work triggers. Confirm understanding and record attendance; a signature alone does not show that workers understood the method.
Review the RAMS when the survey, drawings, removal schedule, isolation status, structural information, tools, access, waste route, occupancy or neighbouring activities change. Also review after a suspect-material discovery, service strike, unexpected movement, dust escape, damage, near miss or concern raised by the workforce.
Can a soft-strip RAMS template be used?
A template can provide headings and a controlled starting structure for routine non-structural strip-out. It cannot know the building, survey limits, structural form, retained items, hidden services, isolations, occupied areas, dust restrictions, waste routes or Principal Contractor requirements.
The Soft Strip / Non-Structural Strip-Out RAMS template is available in the IMERI H&S Partners RAMS shop. Its scope should be checked before purchase and use. A competent person must assess and adapt it to the project, coordinate it with the surveys and project information, and brief the workforce. Buying or completing a template does not make it automatically approved, suitable or site-ready.
If angle grinders or abrasive cutting form part of the actual method, also review the separate angle-grinder and abrasive-cutting guidance; do not assume the soft-strip template covers every cutting arrangement.
When project-specific support is useful
Support is useful where the removal schedule and survey must be reconciled, the building remains occupied, isolations are phased, structural boundaries are unclear, several trades share the area, dust containment is critical or the Principal Contractor has returned generic RAMS for revision.
For projects in Watford, Hertfordshire, London and the South East, send the strip-out drawings and schedule, asbestos and other relevant surveys, service and isolation information, structural constraints, access and waste arrangements, occupied-area controls, programme and Principal Contractor requirements. IMERI H&S Partners can then confirm an appropriate scope for project-specific RAMS support.
Official sources
This guide was checked on 20 October 2026 against current Health and Safety Executive guidance:
- HSE: Contractors—roles and responsibilities under CDM 2015
- HSE: Demolition planning, surveys and sequence
- HSE: Structural stability during alteration, demolition and dismantling
- HSE: Asbestos information and intrusive refurbishment work
- HSE: Construction dust—soft strip demolition
- HSE: Managing electrical risk during refurbishment work
- HSE: Isolation of energy sources