RAMS · Site mobilisation · Welfare maintenance

Site welfare setup and maintenance RAMS: what contractors should include.

Welfare RAMS should connect the approved site layout and workforce needs with the safe delivery, positioning, connection, use, servicing and inspection of the actual facilities throughout the project.

Site welfare RAMS are the safe-work plan for installing and maintaining the chosen facilities; they are not the decision that the facilities are legally sufficient. The Principal Contractor or contractor must first establish what toilets, washing, drinking, changing, drying, eating and rest provision the workforce and work require. The RAMS should then explain how that provision will be delivered, positioned, connected, kept available and safely serviced.

CDM 2015 Schedule 2 sets the minimum welfare facilities required for construction sites. HSE says welfare should be considered early, available from the start of the work and maintained until the project finishes. The separate construction site welfare facilities guide explains that legal baseline. This guide addresses the narrower installation and routine-maintenance method.

Define the facilities, phases and responsibilities

Start with the current site logistics plan, programme, expected maximum workforce, shift pattern, project phases, work locations and the welfare assessment. Identify each facility: toilets, wash stations, changing and drying areas, rest or canteen units, drinking-water points, storage, drying equipment and any satellite or mobile units.

The RAMS should name who controls the compound, accepts deliveries, directs vehicles, checks the prepared base, authorises positioning, connects each service, completes commissioning checks, cleans and replenishes supplies, arranges tank emptying or waste collection, records inspections and closes defects. Hiring a unit or cleaning service does not transfer the duty to verify that the provision remains suitable and available.

Record the hire provider's instructions, unit weights and dimensions, lifting or towing points, service requirements, access needs, tank capacities and operating limits. Confirm whether connections or specialist tasks will be completed under the provider's own reviewed RAMS rather than stretching a general setup method beyond the contractor's competence.

Check the location before a unit is ordered

The proposed compound should be checked against boundaries, ground bearing and level, drainage, buried and overhead services, excavations, lifting zones, scaffold or crane operations, fire and emergency arrangements, traffic routes, pedestrian access, lighting, security and the future construction sequence. Allow safe access for workers, cleaners, maintenance personnel and service vehicles without exposing them to site traffic or workface hazards.

HSE says location decisions should consider whether facilities must move, access for cleaning and maintenance, their distance from the furthest work area and how long workers take to reach them. Large or changing sites may need satellite provision. Facilities should not be placed where later work predictably blocks the door, disconnects services, removes the safe route or traps a servicing vehicle.

Confirm the route and accessibility needs of the expected workforce and visitors. Where delivery drivers wait on site, provide a safe waiting arrangement and safe access to welfare, separated from vehicle movements so far as reasonably practicable.

Plan delivery, unloading and positioning as a separate operation

  1. Book the delivery and confirm the vehicle, load dimensions, unit weight, unloading method, lifting points and ground requirements.
  2. Inspect the route, gate, turning and unloading area; remove conflicts with public access, pedestrians, excavations, overhead restrictions and other deliveries.
  3. Brief the driver, banksman and lifting or handling team on arrival, waiting, exclusion and communication arrangements.
  4. Set an exclusion zone away from passing traffic and people not involved in the operation.
  5. Use suitable equipment and a properly planned lifting operation where mechanical lifting is required; do not improvise from assumed unit weights or unverified attachment points.
  6. Position the unit on the prepared, stable base in the orientation shown on the approved layout, preserving door, step, ramp, window, vent and service clearances.
  7. Secure, level or stabilise the unit in accordance with supplier instructions and the project assessment.
  8. Inspect for delivery damage and prevent use until access, services, safety equipment and welfare functions have been checked and released.

The method should stop the unloading operation if the vehicle, ground, lifting arrangement, weather, access or physical unit differs from the information used to plan it.

Control water, drainage, electrical and heating interfaces

List every proposed connection and its responsible competent person. This may include wholesome drinking-water supplies, washing water, foul drainage, waste or effluent tanks, electricity, lighting, heating, ventilation, data, alarms or other project-specific systems. Confirm connection points, isolation arrangements, protection against damage and the checks required before use.

Electrical supplies and equipment must be suitable for the environment, supply and intended use. HSE advises that supplies should be safe, equipment should be maintained and defective items removed from service. Cables should be routed and protected against damage and trips; electrical installation, alteration and fault finding should remain within the competent contractor's method. An RCD is a secondary protection measure, not permission to use damaged or unsuitable equipment.

Keep drinking-water systems separate from non-potable water and mark supplies where necessary for health or safety. Plan filling, emptying and drainage so hoses, tanks, spills, ice, mud or leaks do not create contamination, slips, blocked access or uncontrolled discharge. Heating appliances, fuelled equipment and generators require their own suitable assessment, ventilation, fuel, fire and maintenance arrangements; a generic welfare RAMS should not authorise installation outside its verified scope.

Describe the routine cleaning and servicing method

A maintenance schedule should reflect workforce numbers, shifts, weather, work type and actual usage rather than relying on one fixed cleaning interval. HSE notes that daily cleaning may not be enough on a muddy site. Define who checks and replenishes toilet paper, soap, hygienic drying, drinking vessels, water, cleaning materials and other consumables.

Before a cleaner or service vehicle enters, confirm the booking, route, parking or exclusion arrangements, key or access control and any changes to the compound. Keep workers away from moving vehicles, hoses and open service points. Use the provider's method for tank emptying, waste transfer, chemical servicing or specialist maintenance, and record spills, leaks, damage or missed visits.

Cleaning products need current safety information and a task-specific COSHH assessment. Do not mix products or decant them into unidentified containers. Segregate wet floors and display effective warnings while cleaning, but remove them when the floor is safe so they do not become permanent background signs. Keep food and rest surfaces separate from contamination and maintain suitable temperatures, ventilation and lighting.

What should be checked and recorded?

Complete a pre-use release check and risk-based routine inspections. The record should cover access and steps or ramps; stability and damage; doors, locks and privacy; lighting, ventilation and temperature; toilets and wash facilities; hot, cold or warm running water as applicable; soap and drying; wholesome drinking water; changing, storage and drying; tables and seating; cleanliness; tanks, drains and leaks; electrical condition; fire and emergency arrangements; consumables; and any facility or route taken out of service.

Set clear action levels. Immediately isolate electrical danger, serious instability, sewage or contaminated-water leaks and any condition that makes a facility unsafe. Provide an effective alternative where a required facility is unavailable; a defect ticket alone does not preserve welfare provision.

Review the layout, welfare assessment and RAMS when workforce numbers, shifts, dirty or hazardous work, access, site traffic, ground, services, provider, equipment or project phase changes. Rebrief affected people after relocation or a material change.

What sits outside routine welfare setup RAMS?

A general method should not cover crane lifting, complex temporary foundations, excavation, work near overhead lines, live electrical work, gas installation, confined-space entry, asbestos disturbance, structural alteration, sewage work or specialist fuel systems unless those activities have been separately designed, planned and assigned to competent people.

It should also not be used to justify inadequate welfare. A chemical toilet and cold-water container are not automatically sufficient, and a mobile unit still has to meet the project's actual Schedule 2 needs. Escalate shortcomings to the Principal Contractor or contractor controlling the construction phase before work relies on the arrangement.

Can a site welfare RAMS template be used?

The Site Welfare Setup & Routine Maintenance RAMS template is currently available in the IMERI H&S Partners RAMS shop as a downloadable digital template. Its verified scope covers welfare layout, delivery or positioning, water, electrical and drainage interfaces, cleaning, replenishment, access and maintenance responsibilities.

A competent person must assess and adapt the template to the site layout, workforce, facilities, suppliers, unit information, ground, delivery, handling, services, servicing schedule, inspections and Principal Contractor requirements, then brief everyone affected. Buying or completing a template does not make it automatically approved, suitable or site-ready.

When is project-specific RAMS support useful?

Support can help where space is constrained, the compound will move between phases, utilities are temporary, welfare is shared between contractors, deliveries interface with the public or the project needs clearer responsibilities and inspection records.

For projects in Watford, Hertfordshire, London and the South East, send the site layout, programme, workforce forecast, facility schedule, unit information, service details, delivery plan, servicing arrangements and deadline. IMERI H&S Partners can then confirm an appropriate scope for project-specific RAMS writing or review.

Official sources

This guide was checked on 13 November 2026 against the following current official sources: