Painting and decorating RAMS should identify the actual areas, substrate condition, preparation, products, application method, access equipment, ventilation, interfaces and finish requirements. They should then explain how dust, hazardous substances, spills, manual handling, work at height, power tools, occupied areas and drying work will be controlled.
Under CDM 2015, contractors must plan, manage and monitor their work, provide suitable supervision and instructions, and coordinate with others. A generic list of hazards does not explain how the specified paint system will be applied safely in the actual rooms or work areas.
The method should align with the relevant parts of the Construction Phase Plan, current drawings and finish schedules, manufacturer instructions, product labels and safety data, COSHH assessments, access arrangements and inspection requirements.
Define the painting and decorating scope precisely
State the rooms, elevations, ceilings, walls, doors, frames, trims or other surfaces included. Record the substrate, its condition, the preparation required, the specified primer and finish coats, and whether the work will be carried out by brush, roller or another approved routine method.
Clarify who repairs defects, releases the substrate, approves samples or colours, isolates services, provides access and accepts each area. Identify whether the premises will be occupied and how residents, employees, visitors and other trades will be kept away from preparation, wet finishes and stored products.
Keep the RAMS within its assessed limits. Routine brush-and-roller decorating RAMS should not be stretched to cover spray application, intumescent or specialist protective coatings, industrial coating removal, disturbance of lead or asbestos, high external work, rope access, confined spaces or other specialist work without separate assessment and competent input.
What information should be obtained before work starts?
Confirm, where relevant:
- the current drawings, room or finish schedule, colour schedule, specification, samples and acceptance criteria;
- the substrate type, age, condition, moisture or contamination concerns, existing coatings and repairs;
- whether uncertain existing materials or coatings require testing or specialist assessment before sanding, scraping, drilling or removal;
- the approved paints, primers, fillers, cleaners and other products, with current labels, safety data and technical information;
- the application method, coverage and drying or recoat conditions stated by the manufacturer;
- the proposed surface-preparation tools, dust controls, power supply, inspection status and competent users;
- the working heights, reach, duration and suitable access equipment for each area;
- ventilation, temperature, lighting, temporary heating and occupied-area constraints;
- product quantities, container sizes, delivery route, secure storage and spill arrangements;
- nearby ignition sources or incompatible work identified by the product information and site rules;
- other trades, occupants, escape routes, alarms, doors, glazing, fixtures and completed finishes; and
- inspection, snagging, protection, waste, room release and handover arrangements.
Do not invent dilution ratios, coverage, drying times, ventilation rates, surface-moisture limits or compatibility. Use the approved specification and current manufacturer information, and raise conflicts before opening or applying the product.
Write the method in the order the work will happen
A project-specific sequence may cover:
- confirming the latest finish information, products, substrate, room release and environmental conditions;
- coordinating deliveries, storage, access, power, lighting, ventilation and segregation;
- checking product containers, labels, tools, cables, extraction and access equipment before use;
- protecting floors, fixtures, alarms, services and adjacent finished work;
- preparing and accepting the substrate using the assessed dust and material controls;
- mixing or preparing only the approved product in accordance with its instructions;
- applying primer and finish coats in the specified order from suitable access equipment;
- maintaining ventilation, exclusion and housekeeping while products dry;
- checking coverage, finish, junctions and defects at the agreed hold points;
- closing containers, cleaning tools in the designated area and managing waste and spill materials;
- removing protection without spreading dust or contaminating the completed finish; and
- recording inspection, snagging, room status and handover.
State who accepts the substrate, authorises product changes, checks the access equipment and releases each area. Responsibilities and hold points make the method usable at the workface.
Critical controls to address in decorating RAMS
Existing surfaces and preparation
Inspect the surface before disturbance. If the identity or condition of an existing coating or material is uncertain, stop and obtain the information or specialist assessment needed. A routine decorating method should not assume that every old finish can safely be dry sanded or scraped.
Choose preparation methods that avoid or reduce dust and debris at source. Where powered sanding is justified, use suitable equipment and effective extraction, separate the work from others and use dust-free cleaning methods. HSE advises vacuuming rather than dry sweeping settled hazardous dust.
Paints, fillers, cleaners and COSHH
A safety data sheet helps identify product hazards, but it is not the COSHH assessment. Assess how the actual product will be opened, mixed, applied, cleaned up and stored; who may be exposed; the routes and duration of exposure; and what controls are required.
Consider whether a less hazardous product or method is suitable. Then define ventilation, containment or segregation, hygiene, spill response, storage, waste and any PPE needed after more reliable controls. Use the product label and safety data to address vapour, mist, skin or eye contact, incompatibility and ignition precautions rather than applying the same controls to every paint.
Ventilation, occupied areas and drying
State how suitable ventilation will be maintained without spreading vapour, odour or dust into occupied or completed areas. Coordinate alarms, fire doors, escape routes, security and any restrictions on opening windows or doors. Do not introduce fans or heaters without considering the product information, electrical loading, air movement and site fire arrangements.
Use barriers and clear signs where others could enter the work area, contact wet finishes or interfere with equipment. Agree when protection can be removed and the room released. The project programme should allow the actual preparation, application and drying process rather than forcing unsafe overlap with other trades or occupants.
Work at height and access
Identify the height, duration, reach and floor condition before choosing access. Suitable podiums, towers, small scaffolds or other equipment may be required. HSE says ladders can be appropriate for low-risk, short-duration work, but they should not automatically be the first choice.
Access equipment should be correctly assembled or positioned, checked as required and protected from unauthorised alteration. Reposition it instead of overreaching. Do not improvise extra height with paint containers, loose boards or unstable items, and keep access away from openings, vehicle routes and unprotected edges.
Manual handling, posture and repetitive work
Assess actual container, tool and access-equipment weights, the delivery route, stairs, repetition, reach and posture. Arrange deliveries close to the work area, use suitable trolleys or team handling where appropriate, keep routes clear and avoid carrying unnecessary quantities.
Plan the work to reduce prolonged overhead application, kneeling, twisting and awkward reach. Suitable equipment, realistic work areas and task rotation can reduce physical demand; manual-handling training alone does not remove the risk.
Tools, electricity and housekeeping
Select preparation tools and electrical equipment that are suitable for the task and environment. Define inspection, guarding, dust extraction, isolation and cable arrangements. Remove damaged equipment from use and isolate it before changing abrasives, clearing blockages or making adjustments.
Trailing leads, dust sheets, open containers, wet paint and waste can create trip, slip and contamination risks. Maintain clear access and escape routes, close containers when not in use, clean spills using the assessed method and remove waste as the work progresses.
Storage, cleaning and waste
Store products in their original labelled containers and in accordance with the safety data, site rules and manufacturer information. Keep quantities proportionate to the work area and secure them from unauthorised access. Where product information identifies flammability or incompatibility, specify the required separation and ignition controls.
Define where brushes, rollers and tools will be cleaned and how residues, contaminated absorbents, empty containers and unused product will be managed. Do not pour paint, solvent or uncontrolled wash water into surface-water drains. Follow the project's approved waste arrangements and product instructions.
How should the RAMS be briefed and reviewed?
The supervisor should brief the workforce on the actual rooms, substrates, products, preparation, application method, access, COSHH controls, ventilation, segregation, sequence, hold points and stop-work conditions. Check understanding at the workface rather than treating signatures as the briefing.
Review the RAMS when the substrate or existing finish differs, a product or application method changes, the work becomes occupied, access changes, ventilation is inadequate, another trade affects the area, the controls are ineffective, or an incident or near miss identifies a gap.
The contractor remains responsible for planning, managing and monitoring its work. A Principal Contractor's review or acceptance does not transfer that duty.
Can a painting and decorating RAMS template be used?
A relevant template can provide a structured starting point, but it cannot know the project's substrates, existing finishes, products, room conditions, access, occupants, work interfaces or Principal Contractor requirements.
The IMERI H&S Partners Painting & Decorating RAMS template is currently available as a digital product. A competent person must check that its scope matches the proposed work, assess the actual project, adapt the hazards, sequence and controls, coordinate it with current design and product information, and brief the workforce.
Buying or downloading a template does not make it approved, suitable for the project or ready to issue. It does not replace the specification, manufacturer instructions, COSHH assessments, access plan, substrate investigation or Principal Contractor review.
When is project-specific RAMS support useful?
Support may be useful where several products or substrates are involved, the premises remain occupied, existing finishes are uncertain, ceiling or high-level work needs planned access, ventilation is restricted, other trades share the rooms, or review comments show that the proposed method is incomplete.
For projects in Watford, Hertfordshire, London and the South East, send the drawings or room schedule, finish specification, substrate information, product data, access requirements, occupied-area constraints, programme and Principal Contractor requirements. IMERI H&S Partners can then confirm an appropriate scope for project-specific RAMS support.
Official sources
- HSE: Contractors—roles and responsibilities under CDM 2015
- HSE: How to carry out a COSHH risk assessment
- HSE: Construction dust
- HSE: Safe use of ladders and stepladders
- HSE: Manual handling—guidance on the Regulations