Metal stud framing RAMS should describe how the actual partition system will be received, stored, set out, cut, assembled, fixed, stabilised, inspected and released for boarding. They should identify the drawings, stud and track specification, dimensions, fixings, openings, supports, tools, access, interfaces, hold points and people responsible for the work.
This is narrower than a complete drylining and plasterboard RAMS. It focuses on the framing that will later be concealed. The RAMS must not invent partition build-ups, fixing centres, deflection heads, reinforcement or support details where the design information is absent or inconsistent.
Define exactly what the framing package includes
State the partition system, locations, maximum heights, stud and track sizes, centres, head and base details, duty rating, openings, noggings, pattressing and any reinforcement included in the contractor's package. Identify whether the work includes shaft-wall framing, independent wall linings, bulkheads, ceilings, acoustic or fire-rated construction, movement joints, door sets or support for fixtures.
Separate standard non-loadbearing partition framing from any structural, loadbearing, unusually tall, curved, external, shaft, riser or temporary works arrangement that needs specialist design or a different method. A familiar product name is not enough to establish the correct build-up or safe sequence.
What information is needed before writing the RAMS?
- current coordinated drawings, partition schedules, specifications and manufacturers' installation details;
- wall height, stud and track sections, centres, head detail, fixings and permitted tolerances;
- approved details for doors, service openings, deflection, movement, bracing, pattressing and interfaces;
- substrate condition, fixing zones and reliable information about concealed services;
- lengths, quantities and bundle weights, delivery point, distribution route and storage arrangements;
- cutting and drilling equipment, blades or accessories, electrical supply, extraction and waste method;
- working heights, platform selection, floor openings and adjacent edge protection;
- interfaces with mechanical, electrical, fire-stopping, doors, ceilings and boarding trades; and
- inspection, recording and release requirements before boarding starts.
Resolve clashes and missing design information before work reaches the affected area. The RAMS can explain how an approved detail will be installed; it should not become an unverified design substitute.
Write the method in the order the framing will be installed
- confirm the current drawings, partition types, work area, interfaces and release to start;
- receive, check and distribute bundles without obstructing access or overloading storage areas;
- set out lines, openings and interfaces against the coordinated information;
- check the fixing zone and concealed-service information before drilling;
- measure and cut track and studs using the selected controlled method;
- install and fix floor, wall and soffit tracks in the specified sequence;
- insert studs, form openings and install noggings, pattressing, bracing or reinforcement where specified;
- coordinate services and preserve required clearances without unauthorised cutting or alteration;
- check line, level, plumb, centres, connections, openings and stability; and
- record the accepted concealed work and release the area for boarding.
Define stop-work points for unexpected services, unsuitable substrates, missing components, design discrepancies, damaged sections, out-of-tolerance work or any framing that will not remain stable before boarding.
Critical controls to address
Bundles, long sections and sharp edges
Assess the actual section lengths, bundle weights, grip, carrying route and frequency. HSE says manual-handling assessments should consider bulky or unstable loads, restricted movement, long carrying distances and harmful features such as sharp edges. Deliver near the workface where practicable, use suitable handling aids for bundles, agree team-handling commands for long sections and keep routes clear.
Store sections on a stable, level support so they cannot slide, roll, topple or project into access routes. Control exposed cut ends and offcuts promptly. Select gloves for the cut and dexterity risks rather than treating any glove as universal protection.
Cutting and powered equipment
Specify the approved cutting method for the section and system. Snips, nibblers, saws or other powered equipment present different cutting, trapping, noise, swarf and ejection risks. Under PUWER, equipment must be suitable, maintained, inspected where necessary, guarded and used by people with adequate information, instruction and training.
Use the correct blade or accessory, keep guards and work supports in place, isolate equipment before adjustment and remove damaged tools from service. Provide eye protection selected for the likely particles. Keep the cutting area segregated and collect sharp offcuts and swarf in a suitable container rather than leaving them on floors or platforms.
Drilling, fixings and concealed services
Use current drawings and an agreed checking method before drilling floors, walls or soffits. HSE warns that electrical cables may be concealed in all three. Where the work could disturb an existing electrical system, arrange suitable isolation or competent advice rather than relying on an assumed cable route.
Plan to reduce unnecessary drilling. Where concrete or masonry drilling remains necessary, assess dust, noise and hand-arm vibration for the actual tool, substrate and duration. Use suitable on-tool extraction or other source control where dust is generated. A dust mask or hearing protection alone does not replace effective engineering and exposure controls.
Access and overhead work
Select access equipment for the height, duration, reach and materials handled. Work at height must be planned, supervised and completed by competent people using appropriate, inspected equipment. Do not stand on loose materials, partition tracks or improvised platforms, and do not overreach while holding long studs or powered tools.
Coordinate high-level fixing with people below and protect floor openings and edges. Keep tools, fixings and sections secured against falling. Moving a podium or tower with a person, loose tools or materials on it should not form part of the method.
Stability, sequencing and other trades
Follow the specified sequence so partially completed framing remains stable. Do not remove components, enlarge openings or cut studs for services unless the current design permits it. Protect frames from impact by material trolleys, mobile plant and other trades, and identify incomplete areas that are not ready for boarding.
Coordinate service routes, door frames, ceilings, fire-stopping and pattressing before close-up. If another trade changes an opening or damages the frame, the area should return to the responsible installer and inspection process rather than being concealed.
What should be inspected before boarding?
Use the approved partition information to check the wall type and location; stud and track sizes; centres and orientation; head, base and abutment fixings; openings; noggings, pattressing and reinforcement; deflection or movement details; line, level and plumb; damage; service interfaces; cleanliness; and any specified fire or acoustic components visible at this stage.
Record the inspection and any photographs required before the work is hidden. State who can release the area and how defects are closed. A signature collected after boarding does not provide evidence that inaccessible framing matched the specified detail.
What should sit outside routine framing RAMS?
A general method should not authorise structural or loadbearing framing, specialist shaft systems, fire-stopping certification, live electrical work, asbestos disturbance, complex temporary stability, hot work, work beside unprotected edges or other activities outside its assessed scope. Obtain the relevant design, permit, specialist method or competent contractor before proceeding.
Can a metal stud partition framing RAMS template be used?
The Metal Stud Partition Framing RAMS template is currently available in the IMERI H&S Partners RAMS shop as a £39.99 downloadable digital template. Its verified scope is assembling metal stud partition framing using the actual system, dimensions, fixings and installation sequence.
A competent person must assess and adapt it to the drawings, system, materials, section lengths, substrates, concealed services, tools, access, interfaces, inspections and Principal Contractor requirements, then brief the workforce. Buying or completing a template does not make it automatically approved, suitable or site-ready.
When is project-specific RAMS support useful?
Support can help where several partition systems are involved, framing is unusually high, service coordination is congested, work is in an occupied building, fixing zones are uncertain or inspection responsibilities are unclear.
For projects in Watford, Hertfordshire, London and the South East, send the partition drawings and schedule, system details, wall heights, substrates, fixings, tools, access method, service interfaces, inspection requirements and deadline. IMERI H&S Partners can then confirm an appropriate scope for project-specific RAMS writing or review.
Official sources
This guide was checked on 13 November 2026 against the following current official sources:
- HSE: manual handling in construction
- HSE: safety in the storage and handling of steel and other metal stock
- HSE: PUWER overview
- HSE: introduction to electrical safety
- HSE: construction dust questions and answers
- HSE: hand-arm vibration controls for fabrication tasks
- HSE: assessing construction noise
- HSE: work at height in construction