Fire stopping installation RAMS: what contractors should include.

Fire-stopping RAMS should explain how the installer will identify the approved detail, verify the opening and services, install the specified tested system, protect the work and create the evidence needed before it is concealed.

Fire-stopping RAMS are an installation plan, not a fire design, product selection exercise or certificate. They should translate the approved drawings, penetration schedule, tested application details and manufacturer instructions into a safe, inspectable method for the actual openings, services, substrates and site conditions.

Part B of Schedule 1 to the Building Regulations 2010 requires appropriate measures to inhibit fire and smoke spread, including unseen spread within concealed spaces. Approved Document B gives practical guidance for England, including fire-stopping joints and openings through fire-separating elements. The project design team must establish what performance and system the construction requires; the installer must not use a generic RAMS document to decide or change that design.

This guide is about construction planning and installation control. It does not offer or replace a fire-risk assessment, a fire-door inspection, building-control approval, design responsibility, third-party certification or the competent inspection of completed work.

Start with the approved design and tested application

Before writing the method, obtain the current fire strategy information relevant to the package, coordinated drawings, compartmentation or penetration schedule, specification, approved details and product-system information. The RAMS should identify the document revisions used and the person who will resolve discrepancies.

For each proposed detail, confirm the fire-separating element, its construction and required performance; the service or joint type; opening size and shape; service size, material and configuration; supports and spacing; annular gap; orientation; backing, sealant or other components; required depth or thickness; movement allowance; and any limitations stated in the tested or assessed application. Use the system manufacturer's current installation instructions for the exact products and configuration.

A product name or performance label is not enough. A system that is suitable for one wall, floor, service material, opening size or orientation may not cover another. The method should prohibit product substitution, mixed systems and undocumented deviations unless the appropriate designer and other responsible parties have reviewed and approved the change.

Use an opening and penetration register

An opening register connects the drawing, physical location, approved detail, installation and evidence. It can be a controlled schedule or digital record, but it should give each item a stable reference and record:

  • building, level, room, grid or other precise location;
  • opening or joint reference and the latest drawing or schedule revision;
  • wall, floor or other fire-separating element and its construction;
  • service type, size, material, number and arrangement;
  • opening dimensions, annular gap and any irregular or oversize condition;
  • specified system, component product names and approved detail reference;
  • installer and installation date;
  • inspection or hold-point status, reviewer and comments;
  • before, during and completed-work photographs where required; and
  • labels, product identification, repair or change records and final acceptance status.

The register should be prepared before installation where practicable and updated as openings are released. A list made only at handover is unlikely to control missing details, concealed work or changes while they can still be corrected.

Set out a controlled installation sequence

  1. Confirm the work area, opening reference, latest approved detail and release to start.
  2. Check the substrate, service configuration, opening dimensions, supports and access against the approved application.
  3. Stop and raise a technical query for damage, missing information, unsuitable construction, excessive gaps, mixed services or any other mismatch.
  4. Verify the specified products, component compatibility, condition, shelf life or use-by controls, batch information where required and manufacturer instructions.
  5. Prepare safe access, lighting, segregation, ventilation, material handling and dust controls without damaging adjacent fire-resisting construction.
  6. Clean and prepare the opening and services using the approved method; protect nearby finishes and active services.
  7. Install every component in the required order, dimensions and position, including backing, supports, collars, wraps, sleeves, boards, compounds or sealants where the specified system requires them.
  8. Complete the defined in-process hold point before any component or face is hidden.
  9. Inspect dimensions, continuity, adhesion, fixings, finish and labelling against the approved detail; record and rectify defects through the agreed process.
  10. Capture the required evidence, update the register and protect the installation until accepted and handed over.

The method should say who may release each hold point and who can accept a repair. It should not use phrases such as “install as necessary” where a measurable, system-specific requirement is available.

Critical controls to address in the RAMS

Competence, supervision and information

Building Regulations duty-holder requirements in England require people carrying out building work to plan, manage and monitor it so that it complies with relevant requirements, cooperate with others and work within their competence. Record the installer competence, product-system training or authorisation where the project requires it, supervisor, inspection responsibility and escalation route. A training card or manufacturer course should not be presented as proof that every configuration is covered.

Brief the team on the approved details, opening references, product instructions, quality hold points, evidence standard, site emergency arrangements and stop-work rules. Make the current information available at the workface and control superseded drawings.

Access and work area

Plan work at height using the hierarchy in the Work at Height Regulations and select equipment that gives stable, hands-free access to the whole opening. Consider voids, risers, ceiling zones, shafts, service congestion, falling objects, sharp edges, heat, poor lighting and restricted egress. Coordinate isolations or permits where work is near live services or other hazardous systems.

Segregate the work and prevent other trades from damaging, removing or covering the installation before inspection. Keep escape routes, temporary fire precautions and site fire arrangements effective throughout the task.

Products, dust and manual handling

Use current safety data and manufacturer instructions to assess sealants, compounds, foams, boards, fibres, cleaners and primers. The COSHH assessment should reflect quantities, application, ventilation, skin and eye contact, curing, spills, waste and the people who may be exposed. Product safety data does not replace a task assessment.

Drilling, trimming or preparing concrete, masonry, boards or existing construction may create harmful dust. Eliminate unnecessary cutting, use suitable extraction or other engineering controls and select any residual RPE from the assessment. Plan the handling and positioning of boards, bags, pails and access equipment; repetitive overhead application can also create musculoskeletal risk.

Existing buildings and unknown construction

Check asbestos information before disturbing existing fabric and confirm the construction behind finishes where the approved detail depends on it. Stop for unidentified materials, damaged compartment walls, hidden openings, unsupported services, undocumented previous repairs or conditions that do not match the survey and drawings.

What inspection and handover evidence should be planned?

Agree the evidence requirement before work starts. It may include the opening register, approved detail, product identification, installer and supervisor details, photographs at defined stages, measured dimensions, inspection results, labels, technical queries, approved deviations, repair records and final location drawings. The project may require additional records, particularly where work is concealed or subject to a formal change-control process.

Photographs should be traceable to the opening and show the information the inspector needs, not merely a close-up of finished sealant. Capture the location and service arrangement, condition before installation, components or backing that will be concealed, completed faces where accessible and the final label or reference where required.

Evidence does not make a non-compliant detail compliant. If the installation differs from the approved application, record the issue and obtain the proper technical decision before it is accepted or covered.

When should installation stop and the RAMS be reviewed?

Stop when the opening, substrate, service, support, orientation, annular gap, access, product, component, drawing or proposed sequence differs from the approved information. Also stop for damaged or expired products, missing components, unidentified services, contamination, wet or otherwise unsuitable substrates, defective access, uncontrolled dust or loss of the inspection hold point.

Raise the issue through the project's technical-query and change-control process. The appropriate designer and other responsible duty holders must decide whether revised design information, a different tested or assessed system, additional preparation or specialist evidence is needed. Update the RAMS, opening register and briefing before restarting.

What sits outside routine fire-stopping installation RAMS?

The installation method should not be stretched to cover fire engineering, selection or design of compartmentation, appraisal of an untested detail, alterations to structural or fire-resisting elements, asbestos work, live electrical work, confined-space entry, specialist access, hot work, fire-door inspection, fire-risk assessment or certification outside the contractor's verified competence and appointment.

Where the work interfaces with drylining, insulation, suspended ceilings or building services, define which contractor prepares the opening, supports the service, installs each component, inspects before close-up and protects the finished system. A gap between packages is still a project risk even when every contractor has its own RAMS.

Can a fire-stopping installation RAMS template be used?

A template can provide structure for the risk assessment, method, responsibilities and briefing, but it cannot select or approve the system for a particular opening.

The Fire Stopping Installation RAMS template is currently available in the IMERI H&S Partners RAMS shop as a downloadable digital template. Its verified product scope is installation to a specified system, with planning prompts for the design, penetration details, substrate, service type, compatibility, competence, access, safety data, inspection evidence and handover records.

A competent person must assess and adapt the template to the project, approved design, tested application, products, openings, services, workforce, access, inspection and Principal Contractor requirements, then brief the people doing the work. Buying or completing a template does not make it automatically approved, suitable, certified or site-ready.

When is project-specific RAMS support useful?

Support can help when multiple systems or service types are involved, work will be concealed in phases, the opening register must connect with project records, or Principal Contractor comments identify unclear responsibilities, hold points or evidence requirements.

For projects in Watford, Hertfordshire, London and the South East, send the package scope, approved drawings and penetration schedule, product-system information, opening and service details, installer information, access, inspection plan, programme and deadline. IMERI H&S Partners can then confirm an appropriate scope for project-specific RAMS writing or review.

Official sources

This guide was checked on 12 November 2026 against the following current official sources: