RAMS · Drainage · Shallow pipework

Drainage & shallow pipework RAMS: what contractors should include.

Routine drainage work can combine buried services, excavation, pipe handling, live connections, testing and backfill in a small work area. This guide explains what contractors should establish before shallow below-ground drainage and pipework installation begins.

Drainage RAMS should define the route, levels, pipe and chamber system, existing services and drainage, excavation and support arrangements, lifting and handling method, laying and jointing sequence, inspections, testing, backfill and clear stop-work limits.

They should be based on the drawings, service information and actual ground and site conditions—not on a generic statement to excavate, lay pipes and backfill. HSE requires contractors to plan, manage and monitor their work so it is carried out without risks to health and safety, coordinating with others and providing suitable supervision, instruction and information.

The task method should align with the site's Construction Phase Plan, permit and service-avoidance arrangements, temporary-works process, traffic plan, emergency procedures and Principal Contractor rules.

Define the drainage work and its limits

State the pipe run, diameters, material, gradients, invert levels, chambers, gullies and connection points. Identify whether the work is in open ground, a building footprint, a road or pedestrian route, an occupied area or close to foundations, scaffolds, plant routes or other excavations.

Describe the excavation depth and width, access and egress, spoil location, support or battering arrangement, dewatering, lifting and lowering method, bedding, jointing, inspection, testing, surround and backfill. Name the responsible supervisor and any hold points at which the work must be checked before it is covered.

Keep routine shallow-drainage RAMS within a defined boundary. They should not be stretched to cover man-entry into a sewer or manhole, a confined space, deep or complex excavation, significant temporary works, pumped bypass, contaminated ground, live highway work or lifting beyond the assessed plant and accessories.

What information should be available before work starts?

Confirm, where relevant:

  • the latest drainage drawings, specification, levels, tolerances, pipe and chamber manufacturer information and approved connection details;
  • current utility plans, client and site records, survey markings and the results of locating and proving existing services;
  • ground conditions, groundwater, contamination, nearby foundations and structures, surcharge loads and weather effects;
  • the excavation dimensions and the competent design or selection of support, battering, edge protection, access and inspection arrangements;
  • plant type, operator competence, lifting accessories, exclusion areas and the safe method for lowering pipes, chambers and covers;
  • delivery, storage and manual-handling arrangements for pipes, fittings, aggregates, chambers and covers;
  • the condition and flow of existing drains, required isolations, hygiene controls and the authorised connection method;
  • cutting and jointing tools, substances, dust and wet-cement controls, ventilation and personal protective equipment;
  • the inspection, test and acceptance method, including any restraint and exclusion needs for pressure or air testing;
  • the specified bedding, surround, backfill, compaction, warning tape or marker requirements and reinstatement; and
  • the emergency response for service damage, collapse, flooding, sewage contact, plant incident or a person entering an unsafe space.

Do not invent service depths, ground strength, trench-support details, lifting weights, pipe gradients or test pressures. Obtain the project and manufacturer information and refer unresolved engineering matters to the competent designer or temporary-works process.

Write the method in the order the work will happen

A project-specific sequence may cover:

  1. checking the latest drawings, permit, services, levels, pipe system, ground conditions, plant and exclusion arrangements;
  2. setting out the route and connection points, locating services and proving them using the agreed safe system before mechanical excavation;
  3. forming and inspecting the excavation in controlled stages, installing support, access, edge and water controls as planned;
  4. preparing the formation and specified bedding without undermining adjacent work or leaving people exposed to an unsupported excavation;
  5. inspecting, handling and lowering pipes, chambers and fittings using the planned equipment and keeping people clear of suspended or uncontrolled loads;
  6. laying and jointing to the specified line, level and orientation, protecting open ends and recording required checks;
  7. making existing-drain connections only under the agreed isolation, flow, hygiene and permit arrangements;
  8. testing and inspecting the installation under the approved procedure, with plugs, restraints and people controlled;
  9. obtaining the hold-point release before placing surround and backfill in the specified layers and compaction sequence; and
  10. reinstating the area, removing controls safely and completing test, inspection and as-built records.

Critical controls to address in drainage RAMS

Buried services and safe excavation

HSE describes three essential parts of a safe system for underground services: planning the work, locating and identifying services, and safe excavation. Plans and locating devices support the work but do not prove that the ground is clear. The RAMS should state how services will be marked, positively identified where necessary and protected, and where hand tools or another controlled technique replaces mechanical excavation.

Stop if the service information conflicts with site findings, markings are lost, an unknown service or duct appears, or the agreed clearance cannot be maintained. Damage reporting and emergency contacts should be available before excavation starts.

Excavation stability, access and inspection

No ground can be assumed to stand unsupported in all conditions. Consider soil, water, depth, duration, nearby foundations, spoil, plant and traffic loads. Use the selected support or safe batter before anyone enters a hazardous area, provide controlled access and edge protection, and keep materials and plant back from the edge.

A competent person should inspect an excavation at the start of each shift and after events that could affect stability, with the report made as required. The work must stop for collapse, cracking, movement, water ingress, damaged support, undermining or any material change until the area is made safe and the method reviewed.

Handling and lowering pipes and chambers

Plan deliveries and storage so pipes cannot roll and components remain within the supplier's limits. Avoid or reduce hazardous manual handling by using suitable lifting points, attachments, pipe hooks, slings, excavator accessories, dollies or team handling selected for the actual load and route.

Keep people out of the drop zone and never use hands or feet beneath a suspended or unstable component to align it. Heavy chamber rings, covers and large pipes need confirmed weights, compatible lifting accessories, adequate plant capacity and a controlled landing method.

Cutting, jointing and hazardous substances

Use the pipe manufacturer's cutting, deburring, lubrication, seal and jointing instructions. Control the workpiece and choose suitable guarded equipment. Cutting concrete or clay products can create respirable crystalline silica; cement-based bedding and concrete can cause serious skin injury; solvent products may require ventilation and ignition controls.

Connect the method to current COSHH assessments and safety data, using dust suppression or extraction, suitable respiratory protection where required, washing arrangements and task-specific PPE. A safety data sheet alone is not a task assessment.

Existing drainage, sewage and hygiene

Confirm what the existing pipe carries, its condition, normal and foreseeable flow, isolation or bypass arrangements and who authorises the connection. Prevent uncontrolled discharge, backflow, flooding and environmental release. Do not rely on a verbal assumption that a pipe is empty or clean.

Where sewage contact is possible, provide suitable gloves and clothing, handwashing, clean and dirty separation, wound care and a clear exposure response. Workers should understand the hygiene risks and avoid hand-to-mouth contamination. Unexpected odour, gas, rising flow, contamination or illness is a stop-work trigger.

Testing, inspection and backfill

Use the specified and approved test procedure. Identify plugs, caps, temporary restraints, pressure limits, test equipment and exclusion areas. People should not stand in line with plugs or fittings that could be displaced. Investigate failure safely rather than increasing pressure or improvising restraints.

Check line, level, falls, joints, connections, chamber construction and test results before covering. Place the specified surround and backfill without displacing or damaging the installation, control compaction near the pipe and record hold-point acceptance, test results and as-built information.

When the routine method must stop and be replaced

Entry into a sewer, manhole, tank or other enclosed area may be confined-space work. HSE says entry should be avoided where possible; where it cannot be avoided, the risks must be assessed and controlled and suitable emergency arrangements must be in place before work starts. A person should never enter merely to retrieve a tool, remove a plug or investigate a blockage under routine shallow-drainage RAMS.

Stop and obtain the correct design, permit and competent input for deep or unstable excavations, complex support, adjacent structures, contaminated ground, pumped bypass, live-carriageway work, unexpected services, significant water ingress or any lifting operation outside the assessed equipment and plan. Revising the document is part of controlling the changed work—not an administrative exercise after it has happened.

Can a drainage RAMS template be used?

A template can provide headings and a controlled starting structure for routine shallow below-ground drainage and pipework. It cannot know the project's services, levels, ground, excavation support, loads, live connections, access restrictions, test requirements or Principal Contractor arrangements.

The Drainage & Shallow Pipework Installation RAMS template is available in the IMERI H&S Partners RAMS shop. Its scope should be checked before purchase and use. A competent person must assess and adapt it to the project, coordinate it with the excavation, temporary-works, lifting and permit arrangements, and brief the workforce. Buying or completing a template does not make it automatically approved, suitable or site-ready.

Also review the wider groundworks RAMS guidance where formation and excavation work extend beyond the drainage installation, and the waste and skip RAMS guidance where excavated materials leave the site.

When project-specific support is useful

Support is useful where service information is incomplete, drainage connects into a live or occupied system, excavation support needs coordination, space or access is restricted, several contractors share the workface, or the Principal Contractor has returned generic RAMS for revision.

For projects in Watford, Hertfordshire, London and the South East, send the drainage drawings, levels and connection details, service information, ground conditions, excavation and support plan, pipe and chamber data, plant, testing requirements and Principal Contractor rules. IMERI H&S Partners can then confirm an appropriate scope for project-specific RAMS support.

Official sources

This guide was checked on 22 October 2026 against current HSE information:

Need project-specific drainage RAMS?

Start with the route, services and excavation plan.

Send the drainage drawings, levels and connections, service information, ground conditions, support plan, plant, testing method and Principal Contractor requirements for a proportionate quotation.