No. Treat a valid CHAS or SSIP certificate as useful first-stage prequalification evidence, then complete a proportionate second-stage check for the actual role and project. Regulation 8 of CDM 2015 requires anyone making a designer or contractor appointment to take reasonable steps to satisfy themselves that the appointee has the necessary skills, knowledge and experience and, for an organisation, organisational capability.
Stage one asks whether the organisation has suitable health and safety management arrangements. Stage two asks whether that organisation can deliver this scope, in this role, with these risks, people, resources and interfaces.
What does a CHAS or SSIP certificate support?
CHAS is an SSIP member scheme. SSIP member schemes assess suppliers against common core criteria for health and safety prequalification. A valid certificate can therefore reduce duplicated first-stage assessment, and HSE supports mutual recognition of current SSIP certification at that stage.
That is valuable evidence, but its scope matters. Check:
- the legal entity and trading identity shown on the certificate;
- that the certification is current and can be verified;
- the assessed work categories and duty-holder roles;
- which scheme or membership level has actually been completed; and
- whether the buyer has specified an additional standard, module or audit.
A logo in a tender document or email signature is not enough. Verify the current record and make sure it applies to the organisation that will contract for and control the work.
What does CDM 2015 still require before appointment?
Regulation 8 applies to the appointment being made. The required capability is therefore connected to the role and the project, not satisfied by a generic badge alone. HSE says the level of skills, knowledge and experience should be proportionate to the complexity of the work and the range and nature of the risks involved.
The same principle applies when a contractor appoints individuals or subcontractors. The contractor must ensure that those carrying out the work have, or are in the process of obtaining, the skills, knowledge, training and experience needed to do it safely. A principal contractor must also plan, manage, monitor and coordinate the construction phase and organise cooperation between contractors.
Do not turn this into an indiscriminate paperwork exercise. “Reasonable steps” should concentrate on the evidence that makes a real difference to the appointment.
What project-specific checks should still be completed?
Start with the role, scope, design information, programme, site constraints and principal risks. Then ask for evidence that addresses those matters directly.
1. Comparable experience and performance
- examples of similar work in scale, complexity, environment and risk;
- references or performance information that can be checked;
- relevant enforcement, incident or improvement information where it is proportionate to the decision; and
- evidence that previous problems were investigated and actions closed.
2. People and supervision
- the proposed contract manager, site manager, supervisors and competent advisers;
- role-relevant qualifications, training, cards, experience and current competence;
- supervisor-to-workforce arrangements suitable for the work; and
- coverage for shifts, absences, specialist activities and emergencies.
3. Resources, plant and specialist controls
- labour, time and logistical resources needed for safe delivery;
- suitable plant, equipment, inspection and maintenance arrangements;
- specialist design, temporary works, lifting, access or occupational-health input where required; and
- a realistic plan for welfare, inductions, consultation and monitoring.
4. Project planning and interfaces
- understanding of the pre-construction information and relevant design risks;
- how the contractor will contribute to the Construction Phase Plan and comply with site arrangements;
- how project-specific RAMS, COSHH assessments, permits and inspection points will be developed and reviewed; and
- how subcontractors, designers, suppliers and neighbouring activities will be coordinated.
Detailed task documents do not always need to be complete at tender stage. The buyer should, however, be satisfied that the contractor understands what must be planned, has allocated ownership and resources, and can produce suitable information before the relevant work begins.
Who is responsible for completing the checks?
The organisation making the appointment must take the reasonable steps required by Regulation 8. On a typical project this may involve several connected decisions:
- the client checks the Principal Designer, Principal Contractor and any designers or contractors it appoints directly;
- the Principal Contractor checks contractors and individuals it appoints, while coordinating those already appointed by the client;
- each contractor checks its own workers and subcontractors; and
- design organisations check the people and specialists they appoint to design work.
Procurement staff can collect evidence, but the technical judgement should involve someone who understands the scope and its risks. A spreadsheet showing “CHAS: yes” is not a substitute for that decision.
How should the competence decision be recorded?
Keep a short, auditable record that explains the decision rather than simply storing attachments. It should identify:
- the organisation, role, scope and work categories assessed;
- the valid CHAS or SSIP evidence checked and the verification date;
- the project-specific evidence reviewed;
- gaps, conditions, actions, owners and due dates;
- who made the judgement and why the evidence was proportionate; and
- what must be confirmed before mobilisation or a high-risk activity starts.
Conditions might include providing named supervisors, completing a lifting plan, resolving a design interface or submitting revised RAMS before the relevant work. Conditions must be tracked and closed; they should not become a list that follows the contractor to site without action.
What should a contractor send to a buyer?
Send the current certificate first, then a concise project-specific capability pack. Include only evidence that helps the buyer understand the proposed team and delivery arrangements:
- the relevant experience summary and checkable references;
- the proposed organisation chart and key-person competence evidence;
- the intended subcontracting and supervision arrangements;
- a response to the project's principal risks and information gaps; and
- the programme for producing task plans, RAMS, design information and other pre-start deliverables.
Keep the general evidence pack current using the CHAS assessment evidence guide. Do not create retrospective records or make unsupported claims simply to secure the appointment.
Official sources
This guide was checked against the current official information available on 14 November 2026:
- The Construction (Design and Management) Regulations 2015, Regulation 8
- HSE: contractor competence and organisational capability
- SSIP: HSE view on prequalification and project-specific scrutiny
- SSIP: appointing competent suppliers
- Veriforce CHAS: client and contractor FAQs
Scheme scope and portal records can change. Verify the current certificate, work categories and buyer requirements. This independent guide is not issued or endorsed by CHAS or SSIP and does not replace project-specific professional judgement.