RAMS · Concrete pumping · Pour coordination

Concrete pumping RAMS: what contractors should include.

Concrete-pumping RAMS should connect the selected pump, setup area, ground and outrigger assessment, delivery route, pipeline, placing gang, pour sequence and emergency arrangements. A supplier's generic pump method does not by itself cover the receiving site or the workface.

Concrete-pumping RAMS should be written around the actual pump, site, pipeline and pour—not copied from a routine concrete-placement method. They should define who controls the pump and pour, confirm a suitable setup and delivery area, prevent access to pressurised lines and the end-hose danger zone, control wet-cement exposure, and state exactly when pumping must stop.

HSE's construction guidance says a method statement should be agreed before formwork and reinforced-concrete work starts and followed during the work. It also highlights formwork release, safe access, even loading and protection from wet concrete. Pumping adds plant, ground, pipeline, pressure, communication and traffic interfaces that need their own assessment.

One coordinated method

The pump operator, concrete supplier, placing contractor and Principal Contractor may each provide information, but the final safe system must join those parts together at the actual site. Sending separate documents without resolving their interfaces leaves a gap.

Define the pumping operation before assessing it

State the pour location and element, concrete specification, estimated volume, planned rate, sequence, start and finish assumptions, required reach and the proposed placing method. Identify whether the operation uses a truck-mounted boom pump, line pump, static pump or another system, and record the exact model once selected.

The RAMS should identify the delivery vehicle type and frequency, pump arrival and departure route, setup and outrigger footprint, pipeline length and route, changes in direction or level, end-hose arrangement, priming method, washout plan and any work beside roads, railways, occupied premises, excavations or overhead services.

Do not extend a method for small direct-discharge or barrowed pours to pumping merely by adding the word “pump”. The site needs enough information to judge plant suitability, ground support, reach, pipeline compatibility, exclusion zones and emergency arrangements.

Who should control each part of the operation?

Record the companies and competent people responsible for the pump, concrete supply, placing gang, pour supervision, traffic control, temporary works and site coordination. Define who is authorised to give start, stop and restart instructions.

InterfaceQuestions the RAMS should answerEvidence or decision
Pump supplierWhich pump, operator, pipeline and manufacturer's limits apply?Plant details, instructions, checks and supplier method.
Principal ContractorIs the route, setup area, traffic plan, exclusion and emergency access acceptable?Site logistics and mobilisation release.
Placing contractorWho directs the pour, handles the hose, vibrates and finishes the concrete?Task roles, briefing and workface controls.
Temporary worksHave formwork, falsework, propping, access and pour rate been released?Required design, inspection and permit-to-pour records.

The contractor preparing the RAMS should reconcile these inputs. “By others” is not an adequate control where the unresolved interface can affect people doing the work.

What should be checked before the pump sets up?

Access, traffic and public protection

Confirm the vehicle route, gate dimensions, turning or reversing arrangements, delivery queue, pedestrian segregation, marshalling, lighting and exit. HSE says construction transport should be planned so vehicles and pedestrians can move safely, with reversing avoided where possible and trained, authorised signallers used where needed.

Ground, outriggers and nearby hazards

  • identify ground conditions, made ground, basements, culverts, chambers, buried services and other voids;
  • keep the plant and outrigger reactions away from unsupported excavation edges or structures unless a suitable assessment permits the setup;
  • use the pump manufacturer's setup limits and the planned spreader or support arrangement;
  • define how level and stability will be checked and maintained during the operation; and
  • confirm that the boom and vehicle cannot enter an overhead-line danger zone or conflict with cranes, scaffolds or structures.

HSE warns that touching an overhead line is not necessary for danger because close approach can cause flashover. The required clearance must be obtained from the network operator where relevant; it should not be guessed from the pump's nominal boom length.

Plant condition and information

Identify the pump, operator and applicable manufacturer instructions. Confirm the supplier's inspection, maintenance and pre-use arrangements, emergency stops, guards, controls and communication equipment. Under PUWER, work equipment must be suitable for its intended use and conditions, maintained in efficient working order, and supported by adequate information and instructions.

How should the pipeline and end hose be controlled?

The pipeline layout should be planned before deliveries begin. Record the pipe and hose types, pressure suitability, couplings, clamps, gaskets, retaining devices, bends, reducers, supports and anchor points required by the supplier's system. Keep access routes and emergency exits clear and protect the line from vehicle impact or unauthorised interference.

  • inspect the complete line and connections before pumping and after alteration;
  • establish an exclusion arrangement for the pipeline, couplings and end-hose movement;
  • position workers so they are not standing astride or over a pressurised line;
  • control the end hose with the people, method and length permitted by the pump supplier;
  • use one agreed communication system between the pump operator and pour team; and
  • prevent the line being opened, disconnected or struck while pressurised.

A blockage is a foreseeable event, not an instruction to improvise. The RAMS should state how pumping stops, how the system is isolated and depressurised, who diagnoses the blockage, how stored pressure is confirmed as released and what supplier method is followed before any connection is disturbed.

Coordinate the pump with the pour and temporary works

Before starting, confirm that required drawings, reinforcement, embeds, formwork, falsework, propping, edge protection, access and inspection hold points are complete and released by the authorised people. A safety review does not replace structural or temporary-works approval.

Connect the agreed pour rate and sequence to the design and workface arrangements. HSE guidance warns against localised loading of wet concrete on temporary structures. Define where concrete will be placed, how the pump or hose will move, how vibration and finishing follow, and how the team prevents reinforcement displacement, formwork overload and loss of safe access.

Coordinate ready-mix arrivals so traffic pressure does not lead to unsafe reversing, blocked emergency routes or rushed decisions. Record how rejected loads, delays, weather changes, lighting loss and potential cold joints will be managed without bypassing the agreed controls.

Control wet-cement exposure and washout

HSE states that wet cement is highly alkaline and can cause serious burns or ulcers, particularly when trapped against the skin. The method should reduce contact and define suitable waterproof gloves, footwear, clothing, washing facilities and accessible eyewash based on the task and current product information.

Explain how splashes are removed promptly, how contaminated clothing is dealt with and how a casualty receives first aid and medical attention. Do not rely on PPE alone where the hose position, work method or exclusion can reduce exposure.

Provide a controlled area and agreed method for priming residues, washout water and returned concrete. Prevent uncontrolled discharge to surface-water drains, public areas or unfinished ground, and keep the washout operation within the supplier's safe shutdown and cleaning procedure.

What should stop the operation?

Give the operator, pour supervisor and relevant site manager clear stop-work authority. Stop, isolate and reassess if:

  • the pump, pipeline, coupling, hose, guard, control or emergency stop is defective;
  • the setup, outrigger support or ground condition changes or shows instability;
  • the boom, vehicle or pipeline could enter an electrical or other prohibited zone;
  • a blockage, pressure surge, hose movement or leak creates uncontrolled risk;
  • people enter the exclusion area or communication is lost;
  • the concrete, pump rate, pour sequence or workface differs from the agreed plan;
  • formwork, falsework, propping, edge protection or access moves or deteriorates; or
  • weather, lighting, traffic or emergency access falls outside the planned conditions.

The RAMS should cover emergency shutdown, concrete exposure, equipment or hose failure, vehicle incident, electrical contact, structural concern and rescue access. Brief the team on who calls the emergency services, the site location, first-aid arrangements and the information the pump supplier needs.

Can a concrete-pumping RAMS template be used?

A template can provide headings, but it cannot know the selected pump, ground, outrigger reactions, pipeline, pressure system, concrete, pour rate, temporary works, traffic, overhead hazards, workface or supplier instructions. It must be project-specifically assessed, adapted, checked and briefed; it is not automatically approved or site-ready.

The current IMERI H&S Partners shop product for routine concrete placement is expressly scoped to small or routine placement tasks and does not confirm coverage for specialist pumping. This guide therefore does not link that product as a concrete-pumping solution.

For the wider pour interface, use the separate concrete placement RAMS guide. Also connect the operation to the delivery and traffic arrangements, temporary-works process and the project's Construction Phase Plan.

For projects in Watford, Hertfordshire, London and the South East, send the drawings, pour schedule, concrete specification, selected pump and supplier method, pipeline proposal, site logistics, ground and setup information, temporary-works release requirements, workforce and deadline. IMERI H&S Partners can then confirm an appropriate scope for project-specific RAMS writing or review.

Official sources

This guide was checked against current official information on 19 November 2026:

This is general Great Britain construction guidance. It is not the pump manufacturer's procedure, a plant inspection, a ground-bearing assessment, temporary-works design, structural approval or a project-specific safe system of work. The contractor and project duty holders must assess the actual operation and obtain competent specialist input where required.

Planning a concrete pump operation?

Join the pump, pipeline, pour and site controls before work starts.

Send the drawings, pour schedule, concrete specification, pump and supplier method, proposed pipeline, logistics plan, ground and temporary-works information, workforce and deadline for a proportionate RAMS quotation.